AI data center · Ellendale, North Dakota

CoreWeave Ellendale ND

CoreWeave's AI campus in Dickey County. It draws about 68 MW today and is planned to reach 520 MW by June 2027.

Power now68 MWAs of Jun 30, 2026
Planned peak520 MWJune 2027
Compute93kH100-equivalent chips now
Capital cost$2.6BSo far, 2025 dollars

Latest look · Jun 30, 2026

What the satellite shows

According to satellite imagery, Building 2 is fully roofed and shell complete, with rooftop chillers mostly installed. Building 3 construction is well underway, with about 1/4 of the roofing done and the foundation laid out.

Build-out

Power, month by month

0 MW200 MW400 MW600 MW2024202520262027Today
Power drawn by CoreWeave Ellendale ND, from Epoch AI's dated observations and (hatched) its projections.
0 MW200 MW400 MW600 MW2024202520262027Today
Power drawn by CoreWeave Ellendale ND, from Epoch AI's dated observations and (hatched) its projections.

Who

Owners, users and builders

Owner
CoreWeave
Used by
OpenAI (speculative)
Chips
B200
Water use
0.00 million gallons a day (Epoch AI estimate)
Address
9685 87th Ave SE, Ellendale, ND 58436
County
Dickey County

Where

On the map of North Dakota

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed by its street address.

Timeline

Every observation

DateWhat Epoch AI sawPower
Jun 30, 2026According to satellite imagery, Building 2 is fully roofed and shell complete, with rooftop chillers mostly installed. Building 3 construction is well underway, with about 1/4 of the roofing done and the foundation laid out.88 MW
Mar 27, 2026According to satellite imagery, Building 1 looks complete and in service, with the surrounding power/cooling equipment also operational. (Note: this image doesn't provide a view of buildings 2 or 3, though it's very safe to assume they're under construction at this stage, considering they're still under construction in the satellite image 3 months from now.)88 MW
Nov 24, 2025This Applied Digital report says the rest of Building 1 has reached Ready for Service, bringing the first building to its expected 100 MW. We can treat this as the first completed data center building.88 MW
Oct 27, 2025The first 50 MW slice of Building 1 has reached Ready for Service status according to this report. This is the first point where we would count any CoreWeave capacity as operational.65 MW
Aug 29, 2025A new 150 MW lease brings CoreWeave to 400 MW total contracted. The project is now clearly scheduled to be a three-building CoreWeave campus.–
May 28, 2025CoreWeave signed the first lease package for 250 MW. No buildings online yet. This is according to an SEC 8-k filing from this date.–
Oct 31, 2023Start of construction for the first building, according to Applied Digital. CoreWeave was not leased yet at this site, but this is the construction start date we're using for relevance.–

Plus 2 projected steps to June 2027, from Epoch AI's reading of the build plans.

How much power does CoreWeave Ellendale ND use?

About 68 MW as of Jun 30, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 520 MW in its build plans by June 2027. Running all year, 68 MW would use about 0.6 TWh.

Who owns CoreWeave Ellendale ND?

CoreWeave; used by OpenAI (speculative). Labels in brackets are Epoch AI's confidence where it is not "confident".

How reliable is the power around CoreWeave Ellendale ND?

In Dickey County, the average customer is without power about 9.3 hours in a typical year in this site's outage record, with 19 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.

Epoch AI's sources for this campus

Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.