AI data center · Ellendale, North Dakota
CoreWeave Ellendale ND
CoreWeave's AI campus in Dickey County. It draws about 68 MW today and is planned to reach 520 MW by June 2027.
Latest look · Jun 30, 2026
What the satellite shows
According to satellite imagery, Building 2 is fully roofed and shell complete, with rooftop chillers mostly installed. Building 3 construction is well underway, with about 1/4 of the roofing done and the foundation laid out.
Build-out
Power, month by month
Who
Owners, users and builders
- Owner
- CoreWeave
- Used by
- OpenAI (speculative)
- Chips
- B200
- Water use
- 0.00 million gallons a day (Epoch AI estimate)
- Address
- 9685 87th Ave SE, Ellendale, ND 58436
- County
- Dickey County
Where
On the map of North Dakota
Placed by its street address.
Timeline
Every observation
| Date | What Epoch AI saw | Power |
|---|---|---|
| Jun 30, 2026 | According to satellite imagery, Building 2 is fully roofed and shell complete, with rooftop chillers mostly installed. Building 3 construction is well underway, with about 1/4 of the roofing done and the foundation laid out. | 88 MW |
| Mar 27, 2026 | According to satellite imagery, Building 1 looks complete and in service, with the surrounding power/cooling equipment also operational. (Note: this image doesn't provide a view of buildings 2 or 3, though it's very safe to assume they're under construction at this stage, considering they're still under construction in the satellite image 3 months from now.) | 88 MW |
| Nov 24, 2025 | This Applied Digital report says the rest of Building 1 has reached Ready for Service, bringing the first building to its expected 100 MW. We can treat this as the first completed data center building. | 88 MW |
| Oct 27, 2025 | The first 50 MW slice of Building 1 has reached Ready for Service status according to this report. This is the first point where we would count any CoreWeave capacity as operational. | 65 MW |
| Aug 29, 2025 | A new 150 MW lease brings CoreWeave to 400 MW total contracted. The project is now clearly scheduled to be a three-building CoreWeave campus. | – |
| May 28, 2025 | CoreWeave signed the first lease package for 250 MW. No buildings online yet. This is according to an SEC 8-k filing from this date. | – |
| Oct 31, 2023 | Start of construction for the first building, according to Applied Digital. CoreWeave was not leased yet at this site, but this is the construction start date we're using for relevance. | – |
Plus 2 projected steps to June 2027, from Epoch AI's reading of the build plans.
How much power does CoreWeave Ellendale ND use?
About 68 MW as of Jun 30, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 520 MW in its build plans by June 2027. Running all year, 68 MW would use about 0.6 TWh.
Who owns CoreWeave Ellendale ND?
CoreWeave; used by OpenAI (speculative). Labels in brackets are Epoch AI's confidence where it is not "confident".
How reliable is the power around CoreWeave Ellendale ND?
In Dickey County, the average customer is without power about 9.3 hours in a typical year in this site's outage record, with 19 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.
Epoch AI's sources for this campus
- Applied Digital Announces 250MW AI Data Center Lease With CoreWeave
- SEC 8k Filing with Applied Digital
- Applied Digital Delivers Second Building at Polaris Forge 1
Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.