AI data center · Manassas, Virginia

STACK Infrastructure NVA02

AI campus in Prince William County. It draws about 85 MW today and is planned to reach 487 MW by January 2028.

Power now85 MWAs of Feb 14, 2026
Planned peak487 MWJanuary 2028
Compute61kH100-equivalent chips now
Capital cost$3.2BSo far, 2025 dollars

Latest look · Feb 14, 2026

What the satellite shows

All buildings have begun construction (with groundwork starting for AI building 6), as depicted by satellite imagery.

Build-out

Power, month by month

0 MW200 MW400 MW600 MW202020212022202320242025202620272028Today
Power drawn by STACK Infrastructure NVA02, from Epoch AI's dated observations and (hatched) its projections.
0 MW200 MW400 MW600 MW20202022202420262028Today
Power drawn by STACK Infrastructure NVA02, from Epoch AI's dated observations and (hatched) its projections.

Who

Owners, users and builders

Chips
H100
Address
9590 Hornbaker Rd, Manassas, VA 20109
County
Prince William County

Where

On the map of Virginia

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed by its street address.

Nearby

Power plants within 15 miles

PlantSourceCapacityDistance
Energix Nokesville, LLC● Solar20 MW6.2 mi
Dominion/Lo Mar● Oil19 MW2.1 mi
VMEA 1 Credit Gen● Oil13 MW1.6 mi
VMEA Peaking Gen● Oil6 MW1.6 mi
Godwin Drive Plant● Oil6 MW1.6 mi
Church Street Plant● Oil4 MW3.9 mi
Gateway Gen● Oil4 MW2.2 mi
VA- US Foods- Manassas● Solar2 MW2.7 mi

Timeline

Every observation

DateWhat Epoch AI sawPower
Feb 14, 2026All buildings have begun construction (with groundwork starting for AI building 6), as depicted by satellite imagery.118 MW
Oct 1, 2024Building 1 is operational, which is assumed to be three months after the last backup diesel generators are finished. The generators were first seen to be finished July 1 from satellite imagery (a clear image of this can be seen on July 29 via Google Earth).118 MW
Oct 19, 2019Land clearing begins by Peterson Companies for Stack Infrastructure, which is noted in the news and visible on satellite imagery.–

Plus 1 projected step to January 2028, from Epoch AI's reading of the build plans.

How much power does STACK Infrastructure NVA02 use?

About 85 MW as of Feb 14, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 487 MW in its build plans by January 2028. Running all year, 85 MW would use about 0.7 TWh.

How reliable is the power around STACK Infrastructure NVA02?

In Prince William County, the average customer is without power about 1.8 hours in a typical year in this site's outage record, with 2 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.

What power plants are near STACK Infrastructure NVA02?

8 plants within 15 miles total about 77 MW; the largest is Energix Nokesville, LLC (20 MW, solar), 6.2 miles away. Nearness does not mean it supplies the campus.

Epoch AI's sources for this campus

Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.