AI data center · Bristow, Virginia
Google Bristow
Google's AI campus in Prince William County. It draws about 238 MW today and is planned to reach 286 MW by May 2026.
Latest look · May 20, 2026
What the satellite shows
Building 3 is operational, based off of colored motion artifacts from cooling towers.
Build-out
Power, month by month
Who
Owners, users and builders
- Owner
- Used by
- Google DeepMind
- Chips
- TPU v5e, TPU v5p, TPU v6e, TPU v7
- Address
- 13001 Rollins Ford Road, Bristow, VA 20136
- County
- Prince William County
Where
On the map of Virginia
Placed by its street address.
Nearby
Power plants within 15 miles
| Plant | Source | Capacity | Distance |
|---|---|---|---|
| Energix Nokesville, LLC | ● Solar | 20 MW | 7.7 mi |
| Dominion/Lo Mar | ● Oil | 19 MW | 5.2 mi |
| VMEA 1 Credit Gen | ● Oil | 13 MW | 4.8 mi |
| VMEA Peaking Gen | ● Oil | 6 MW | 4.8 mi |
| Godwin Drive Plant | ● Oil | 6 MW | 4.8 mi |
| Church Street Plant | ● Oil | 4 MW | 6.6 mi |
| Gateway Gen | ● Oil | 4 MW | 5.5 mi |
| VA- US Foods- Manassas | ● Solar | 2 MW | 1.4 mi |
Timeline
Every observation
| Date | What Epoch AI saw | Power |
|---|---|---|
| May 20, 2026 | Building 3 is operational, based off of colored motion artifacts from cooling towers. | 286 MW |
| Apr 29, 2025 | Building 2 is operational, based off it being at least 12 months since the roof was complete. Building 3 is finishing construction of cooling towers. | 208 MW |
| Apr 29, 2024 | Building 1 is operational, based off of colored motion artifacts from cooling towers. Building 2 is undergoing construction. | 104 MW |
| Jul 1, 2021 | Land clearing begins. | – |
How much power does Google Bristow use?
About 238 MW as of May 20, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 286 MW in its build plans by May 2026. Running all year, 238 MW would use about 2.1 TWh.
Who owns Google Bristow?
Google; used by Google DeepMind. Labels in brackets are Epoch AI's confidence where it is not "confident".
How reliable is the power around Google Bristow?
In Prince William County, the average customer is without power about 1.8 hours in a typical year in this site's outage record, with 2 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.
What power plants are near Google Bristow?
8 plants within 15 miles total about 77 MW; the largest is Energix Nokesville, LLC (20 MW, solar), 7.7 miles away. Nearness does not mean it supplies the campus.
Epoch AI's sources for this campus
Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.