AI data center · Sandston, Virginia

QTS Richmond 2

AI campus in Henrico County. It draws about 180 MW today and is planned to reach 252 MW by May 2026.

Power now180 MWAs of May 14, 2026
Planned peak252 MWMay 2026
Compute183kH100-equivalent chips now
Capital cost$6.8BSo far, 2025 dollars

Latest look · May 14, 2026

What the satellite shows

Building 5 is estimated to be operational, based on the previous entry.

Build-out

Power, month by month

0 MW100 MW200 MW300 MW2023202420252026
Power drawn by QTS Richmond 2, from Epoch AI's dated observations.
0 MW100 MW200 MW300 MW2023202420252026
Power drawn by QTS Richmond 2, from Epoch AI's dated observations.

Who

Owners, users and builders

Energy companies
Dominion Energy
Water use
0.00 million gallons a day (Epoch AI estimate)
Address
6030–6070 Technology Blvd, Sandston, VA 23150
County
Henrico County (approximate)

Where

On the map of Virginia

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed at the centre of Sandston, as no address could be matched, so the dot and the county are approximate.

Nearby

Power plants within 15 miles

PlantSourceCapacityDistance
Chesterfield● Natural gas447 MW9.8 mi
Darbytown● Natural gas368 MW3.2 mi
Skipjack Solar Center● Solar175 MW10 mi
Keydet Solar Center● Solar120 MW10 mi
Spruance Operating Services LLC● Natural gas115 MW7.6 mi
Hopewell Power Station● Biomass71 MW15 mi
Mechanicsville Solar● Solar25 MW12 mi
Briel Solar Farm● Solar20 MW2.8 mi

Timeline

Every observation

DateWhat Epoch AI sawPower
May 14, 2026Building 5 is estimated to be operational, based on the previous entry.252 MW
Feb 13, 2026Building 5 still has construction work at the perimeter, but given how close it looks to completion, we estimate it's only about 3 months away from operational.202 MW
Dec 31, 2025Building 3 and 4 are operational, based on the substation being completed earlier, the buildings looking complete, and carparks being moderately full. Building 5 still has construction work.202 MW
Nov 19, 2025The west substation looks complete, based on a Google Earth image. This image also shows one corner of Building 5 that still has construction work, so it's probably not operational.101 MW
Feb 4, 2025Building 1 and 2 are operational, based on the east substation looking complete and the carparks being more full. Building 3 has cooling and generators mostly installed. Building 4 roof is partly completed.101 MW
Jun 23, 2024Still not many cars parked at Building 1 and 2, and the east substation looks very close to completion, based on a Google Earth image.–
Jan 29, 2024Building 1 and 2 look complete but we don't think they are operational, as the substation is still under construction.–
Apr 1, 2022Land clearing begins.–

How much power does QTS Richmond 2 use?

About 180 MW as of May 14, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 252 MW in its build plans by May 2026. Running all year, 180 MW would use about 1.6 TWh.

How reliable is the power around QTS Richmond 2?

In Henrico County, the average customer is without power about 10 hours in a typical year in this site's outage record, with 12 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.

What power plants are near QTS Richmond 2?

8 plants within 15 miles total about 1.42 GW; the largest is Chesterfield (447 MW, natural gas), 9.8 miles away. Nearness does not mean it supplies the campus.

Epoch AI's sources for this campus

Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.