AI data center · Sandston, Virginia

QTS Richmond 3

AI campus in Henrico County. It draws about 144 MW today and is planned to reach 336 MW by February 2027.

Power now144 MWAs of May 14, 2026
Planned peak336 MWFebruary 2027
Compute175kH100-equivalent chips now
Capital cost$5.5BSo far, 2025 dollars

Latest look · May 14, 2026

What the satellite shows

Building 2 and 3 are operational, based on the previous entry.

Build-out

Power, month by month

0 MW100 MW200 MW300 MW400 MW202520262027Today
Power drawn by QTS Richmond 3, from Epoch AI's dated observations and (hatched) its projections.
0 MW100 MW200 MW300 MW400 MW202520262027Today
Power drawn by QTS Richmond 3, from Epoch AI's dated observations and (hatched) its projections.

Who

Owners, users and builders

Energy companies
Dominion Energy
Address
3525–3543 Portugee Rd, Sandston, VA 23150
County
Henrico County (approximate)

Where

On the map of Virginia

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed at the centre of Sandston, as no address could be matched, so the dot and the county are approximate.

Nearby

Power plants within 15 miles

PlantSourceCapacityDistance
Chesterfield● Natural gas447 MW9.8 mi
Darbytown● Natural gas368 MW3.2 mi
Skipjack Solar Center● Solar175 MW10 mi
Keydet Solar Center● Solar120 MW10 mi
Spruance Operating Services LLC● Natural gas115 MW7.6 mi
Hopewell Power Station● Biomass71 MW15 mi
Mechanicsville Solar● Solar25 MW12 mi
Briel Solar Farm● Solar20 MW2.8 mi

Timeline

Every observation

DateWhat Epoch AI sawPower
May 14, 2026Building 2 and 3 are operational, based on the previous entry.202 MW
Feb 13, 2026Building 1 is operational, based on the substation being completed earlier and cars in the carpark. Building 2 and 3 are not operational, based on minor construction work at the perimeter and no cars in the carpark, but we expect they will be operational within 3 months. Building 4 has complete chillers and backup generators, while Building 5 has chillers but only a few backup generators - roughly the state of Building 1 on 2025-02-04.67 MW
Dec 31, 2025The substation looks complete, but we expect Building 1 still needs commissioning before it is fully operational.–
Nov 19, 2025The substation is still under construction, based on a Google Earth image, so we don't think any buildings are operational yet.–
Feb 4, 2025Building 1 shell is mostly complete, with some chillers installed on the roof. Building 2 shell is under construction.–
Apr 1, 2024Land clearing begins.–

Plus 1 projected step to February 2027, from Epoch AI's reading of the build plans.

How much power does QTS Richmond 3 use?

About 144 MW as of May 14, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 336 MW in its build plans by February 2027. Running all year, 144 MW would use about 1.3 TWh.

How reliable is the power around QTS Richmond 3?

In Henrico County, the average customer is without power about 10 hours in a typical year in this site's outage record, with 12 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.

What power plants are near QTS Richmond 3?

8 plants within 15 miles total about 1.42 GW; the largest is Chesterfield (447 MW, natural gas), 9.8 miles away. Nearness does not mean it supplies the campus.

Epoch AI's sources for this campus

Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.