AI data center · Sandston, Virginia

QTS Richmond 1

AI campus in Henrico County. It draws about 238 MW today and is planned to reach 333 MW by November 2025.

Power now238 MWAs of Feb 13, 2026
Planned peak333 MWNovember 2025
Compute243kH100-equivalent chips now
Capital cost$9.0BSo far, 2025 dollars

Latest look · Feb 13, 2026

What the satellite shows

No changes to the site since December 2025.

Build-out

Power, month by month

0 MW100 MW200 MW300 MW400 MW202420252026
Power drawn by QTS Richmond 1, from Epoch AI's dated observations.
0 MW100 MW200 MW300 MW400 MW202420252026
Power drawn by QTS Richmond 1, from Epoch AI's dated observations.

Who

Owners, users and builders

Energy companies
Dominion Energy
Address
6000 Technology Blvd, Sandston, VA 23150
County
Henrico County

Where

On the map of Virginia

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed by its street address.

Nearby

Power plants within 15 miles

PlantSourceCapacityDistance
Chesterfield● Natural gas447 MW10.5 mi
Hopewell Cogeneration● Natural gas399 MW13.7 mi
Darbytown● Natural gas368 MW6.7 mi
Skipjack Solar Center● Solar175 MW6 mi
Keydet Solar Center● Solar120 MW6 mi
Spruance Operating Services LLC● Natural gas115 MW10.3 mi
Hopewell Power Station● Biomass71 MW13.3 mi
Hopewell Mill● Biomass48 MW13.8 mi

Timeline

Every observation

DateWhat Epoch AI sawPower
Feb 13, 2026No changes to the site since December 2025.333 MW
Dec 31, 2025No changes to the site since November 2025.333 MW
Nov 19, 2025Building 5 is operational, based on a complete building and full carpark in a Google Earth image. Construction equipment around Building 1 and 2 has cleared up again.333 MW
Jun 3, 2025Building 4 is operational, based on a complete building and full carpark in a Google Earth image. Building 5 does not seem quite operational given the empty carpark and construction activity at the perimeter.266 MW
Feb 4, 2025Building 3 is operational, based on the building looking complete and the carpark to the south being full. Three more backup generators added to the Building 1 and 2 area, with a lot more construction equipment again (but this could be a laydown area for Richmond 2). Building 4 has cooling and backup generators fully installed. Building 5 has cooling installed, and backup generators partly installed.199 MW
Jun 23, 2024Building 2 (retrofitted) is operational. This is based on Building 2 looking compelte, and construction around Building 1 and 2 being mostly cleared. A colored motion artifact on one of the Building 1 cooling tower fans suggests it is moving. Building 3 cooling is installed, backup generators partly installed. Building 4 shell is under construction.132 MW
Jan 29, 2024Building 1 (retrofitted) is operational. This is based on it looking complete, and cooling towers possibly showing water vapor plumes, in this Google Earth image. Building 2 has chillers added to the roof and perimeter, and backup generators added to the perimeter. Cooling towers near Building 2 have been removed. Building 3 shell is under construction.66 MW
Nov 2, 2023Building 1 and 2 retrofitting has begun (see Google Earth). Building 1 has chillers added to the roof and perimeter, and backup generators added to the perimeter.–
Sep 1, 2023Land clearing begins for site expansion, some materials down at substation site. We assume that Buildings 1 and 2 are not running AI workloads at this point due to the lack of cooling infrastructure.–

How much power does QTS Richmond 1 use?

About 238 MW as of Feb 13, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 333 MW in its build plans by November 2025. Running all year, 238 MW would use about 2.1 TWh.

How reliable is the power around QTS Richmond 1?

In Henrico County, the average customer is without power about 10 hours in a typical year in this site's outage record, with 12 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.

What power plants are near QTS Richmond 1?

8 plants within 15 miles total about 1.86 GW; the largest is Chesterfield (447 MW, natural gas), 10.5 miles away. Nearness does not mean it supplies the campus.

Epoch AI's sources for this campus

Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.