AI data center · Chester, Virginia
CoreWeave Chester VA
CoreWeave's AI campus in Chesterfield County. It draws about 82 MW today and is planned to reach 197 MW by June 2027.
Latest look · May 20, 2026
What the satellite shows
Based on satellite imagery, Building 3 has cleared its land and is beginning construction. Building 2 is operational judging from the colored motion artifacts on the cooling tower fans.
Build-out
Power, month by month
Who
Owners, users and builders
- Owner
- CoreWeave
- Used by
- OpenAI (speculative)
- Chips
- H100, B200
- Address
- 1401 Meadowville Technology Parkway, Chester, VA
- County
- Chesterfield County
Where
On the map of Virginia
Placed by its street address.
Nearby
Power plants within 15 miles
| Plant | Source | Capacity | Distance |
|---|---|---|---|
| Chesterfield | ● Natural gas | 447 MW | 3.5 mi |
| Hopewell Cogeneration | ● Natural gas | 399 MW | 5.4 mi |
| Darbytown | ● Natural gas | 368 MW | 9.7 mi |
| Skipjack Solar Center | ● Solar | 175 MW | 10.5 mi |
| Keydet Solar Center | ● Solar | 120 MW | 10.5 mi |
| Spruance Operating Services LLC | ● Natural gas | 115 MW | 8.7 mi |
| Hopewell Power Station | ● Biomass | 71 MW | 5 mi |
| Hopewell Mill | ● Biomass | 48 MW | 5.4 mi |
Timeline
Every observation
| Date | What Epoch AI saw | Power |
|---|---|---|
| May 20, 2026 | Based on satellite imagery, Building 3 has cleared its land and is beginning construction. Building 2 is operational judging from the colored motion artifacts on the cooling tower fans. | 114 MW |
| Jan 22, 2025 | Satellite imagery shows Building 1 complete, with Building 2's yard work and early construction visible. Building 3 hasn't started yet, since the old building is still there. | 38 MW |
| Apr 30, 2024 | Building 1 is scheduled to be fully online by this point, so we count the full 27 MW as operational here. | 38 MW |
| Jan 31, 2024 | Building 1's second data hall scheduled to come online this month. | 25 MW |
| Sep 18, 2023 | Conversion starts at CTP-01 (Building 1). The data center was formerly owned by Capital One, now leased to CoreWeave. Source: https://www.datacenterdynamics.com/en/news/chirisa-secures-200-million-loan-to-fit-out-virginia-data-center-for-coreweave/ | – |
Plus 1 projected step to June 2027, from Epoch AI's reading of the build plans.
How much power does CoreWeave Chester VA use?
About 82 MW as of May 20, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 197 MW in its build plans by June 2027. Running all year, 82 MW would use about 0.7 TWh.
Who owns CoreWeave Chester VA?
CoreWeave; used by OpenAI (speculative). Labels in brackets are Epoch AI's confidence where it is not "confident".
How reliable is the power around CoreWeave Chester VA?
In Chesterfield County, the average customer is without power about 7.4 hours in a typical year in this site's outage record, with 8 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.
What power plants are near CoreWeave Chester VA?
8 plants within 15 miles total about 1.85 GW; the largest is Chesterfield (447 MW, natural gas), 3.5 miles away. Nearness does not mean it supplies the campus.
Epoch AI's sources for this campus
- Chirisa secures $200 million loan to fit out VA Data center for CoreWeave
- Blue Owl-led JV secures $750m to build out data centers for CoreWeave
- Chirisa offers former Capital One data center in Virginia to hyperscalers
Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.