AI data center · Clark, Nevada
Google Storey County
Google's AI campus in Storey County. It draws about 161 MW today and is planned to reach 389 MW by June 2027.
Latest look · Apr 13, 2026
What the satellite shows
Building 3 has a partially complete shell, electrical and mechanical equipment. Building 4 foundation is underway.
Build-out
Power, month by month
Who
Owners, users and builders
- Owner
- Used by
- Google DeepMind (speculative)
- Chips
- TPU v5e, TPU v4, TPU v6e, TPU v5p
- Water use
- 0.00 million gallons a day (Epoch AI estimate)
- County
- Storey County
Where
On the map of Nevada
Placed at the industrial area or township Epoch's sources name; the exact site is not mapped here.
Nearby
Power plants within 15 miles
| Plant | Source | Capacity | Distance |
|---|---|---|---|
| Tracy | ● Natural gas | 1.03 GW | 1.9 mi |
| Western 102 Power Plant | ● Natural gas | 119 MW | 1.1 mi |
| Turquoise Nevada, LLC | ● Solar | 60 MW | 2.2 mi |
| Turquoise Liberty Solar | ● Solar | 10 MW | 2.8 mi |
| Chukar Battery Energy Storage System | ● Storage | 10 MW | 2.9 mi |
| Tesla Reno GigaFactory | ● Solar | 7 MW | 3 mi |
| Waste Management Lockwood LFGTE | ● Biomass | 3 MW | 8.2 mi |
Timeline
Every observation
| Date | What Epoch AI saw | Power |
|---|---|---|
| Apr 13, 2026 | Building 3 has a partially complete shell, electrical and mechanical equipment. Building 4 foundation is underway. | 214 MW |
| Sep 28, 2025 | Building 3 foundation is underway. Building 2 exterior looks totally clean/landscaped. | 214 MW |
| Jun 30, 2025 | Building 2 is operational. Based on a Google Earth image showing complete building shell, mechanical equipment and generators, plus cars parked at the front. | 214 MW |
| Mar 11, 2025 | Building 2 now has generators in place, but there is still a crane and construction work present. | 107 MW |
| Aug 30, 2023 | Building 1, which was first operational in 2021, has increased power capacity by about 75%. This is based on the expansion of the dry cooling array from 4 to 7 columns (seen on Google Earth). Its backup generators also grew from 18 to 33, an 83% increase. Around this time (2023 Q3) the quarterly PUE of the campus is 1.24, down from the initial 1.29 in 2022 Q3. Since no other buildings have been added, these changes indicate an increase in power density, which may entail a new generation of hardware getting installed. | 107 MW |
| Mar 18, 2019 | Land clearing begins. | – |
Plus 1 projected step to June 2027, from Epoch AI's reading of the build plans.
How much power does Google Storey County use?
About 161 MW as of Apr 13, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 389 MW in its build plans by June 2027. Running all year, 161 MW would use about 1.4 TWh.
Who owns Google Storey County?
Google; used by Google DeepMind (speculative). Labels in brackets are Epoch AI's confidence where it is not "confident".
How reliable is the power around Google Storey County?
In Storey County, the average customer is without power about 7.6 hours in a typical year in this site's outage record, with 15 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.
What power plants are near Google Storey County?
7 plants within 15 miles total about 1.24 GW; the largest is Tracy (1.03 GW, natural gas), 1.9 miles away. Nearness does not mean it supplies the campus.
Epoch AI's sources for this campus
- Air quality permit application listing emergency generators and a small "R&D" fuel cell plant
- Aterio
- Google data center page
Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.