AI data center · Clark, Nevada

Google Storey County

Google's AI campus in Storey County. It draws about 161 MW today and is planned to reach 389 MW by June 2027.

Power now161 MWAs of Apr 13, 2026
Planned peak389 MWJune 2027
Compute134kH100-equivalent chips now
Capital cost$6.1BSo far, 2025 dollars

Latest look · Apr 13, 2026

What the satellite shows

Building 3 has a partially complete shell, electrical and mechanical equipment. Building 4 foundation is underway.

Build-out

Power, month by month

0 MW100 MW200 MW300 MW400 MW500 MW20202021202220232024202520262027Today
Power drawn by Google Storey County, from Epoch AI's dated observations and (hatched) its projections.
0 MW100 MW200 MW300 MW400 MW500 MW2021202320252027Today
Power drawn by Google Storey County, from Epoch AI's dated observations and (hatched) its projections.

Who

Owners, users and builders

Owner
Google
Used by
Google DeepMind (speculative)
Chips
TPU v5e, TPU v4, TPU v6e, TPU v5p
Water use
0.00 million gallons a day (Epoch AI estimate)
County
Storey County

Where

On the map of Nevada

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed at the industrial area or township Epoch's sources name; the exact site is not mapped here.

Nearby

Power plants within 15 miles

PlantSourceCapacityDistance
Tracy● Natural gas1.03 GW1.9 mi
Western 102 Power Plant● Natural gas119 MW1.1 mi
Turquoise Nevada, LLC● Solar60 MW2.2 mi
Turquoise Liberty Solar● Solar10 MW2.8 mi
Chukar Battery Energy Storage System● Storage10 MW2.9 mi
Tesla Reno GigaFactory● Solar7 MW3 mi
Waste Management Lockwood LFGTE● Biomass3 MW8.2 mi

Timeline

Every observation

DateWhat Epoch AI sawPower
Apr 13, 2026Building 3 has a partially complete shell, electrical and mechanical equipment. Building 4 foundation is underway.214 MW
Sep 28, 2025Building 3 foundation is underway. Building 2 exterior looks totally clean/landscaped.214 MW
Jun 30, 2025Building 2 is operational. Based on a Google Earth image showing complete building shell, mechanical equipment and generators, plus cars parked at the front.214 MW
Mar 11, 2025Building 2 now has generators in place, but there is still a crane and construction work present.107 MW
Aug 30, 2023Building 1, which was first operational in 2021, has increased power capacity by about 75%. This is based on the expansion of the dry cooling array from 4 to 7 columns (seen on Google Earth). Its backup generators also grew from 18 to 33, an 83% increase. Around this time (2023 Q3) the quarterly PUE of the campus is 1.24, down from the initial 1.29 in 2022 Q3. Since no other buildings have been added, these changes indicate an increase in power density, which may entail a new generation of hardware getting installed.107 MW
Mar 18, 2019Land clearing begins.–

Plus 1 projected step to June 2027, from Epoch AI's reading of the build plans.

How much power does Google Storey County use?

About 161 MW as of Apr 13, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 389 MW in its build plans by June 2027. Running all year, 161 MW would use about 1.4 TWh.

Who owns Google Storey County?

Google; used by Google DeepMind (speculative). Labels in brackets are Epoch AI's confidence where it is not "confident".

How reliable is the power around Google Storey County?

In Storey County, the average customer is without power about 7.6 hours in a typical year in this site's outage record, with 15 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.

What power plants are near Google Storey County?

7 plants within 15 miles total about 1.24 GW; the largest is Tracy (1.03 GW, natural gas), 1.9 miles away. Nearness does not mean it supplies the campus.

Epoch AI's sources for this campus

Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.