Data centers · Maryland

Data centers in Maryland

26 operating data center sites, 12 projects planned or under construction.

Operating sites260 whole campuses
AI campuses0None tracked by Epoch AI
In the pipeline123 under construction, 9 planned
Home price19.5¢/kWh+47% since 2018

The map

Every mapped site

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI) Under construction Planned Cancelled

The pipeline

Projects on the way

From Civic Returns, Server Country, AI GridWatch, Megawattlas and the operators' own lists. Size is the developer's announced figure, often a full build-out over years. Projects with no published location are mapped at their city or county.

ProjectDeveloperCountyStatusAnnounced sizeYear
Aligned Quantum Frederick campus Aligned Frederick Under construction 264 MW –
Bauxite Data Center 1 Rowan Digital Infrastructure Frederick Under construction 231 MW 2026
Bauxite Data Center 3 Rowan Digital Infrastructure Frederick Under construction – 2027
Brightseat Tech Park Lerner Enterprises Prince George's Planned 820 MW –
TeraWulf - Chesapeake Data & Energy TeraWulf Charles Planned 800 MW 2030
AWS Calvert Cliffs Data Center Campus Amazon Web Services Calvert Planned 500 MW –
Dickerson Power Plant Data Center Proposals Terra Energy, LLC Montgomery Planned 360 MW –
Natelli Holdings - Appeal Digital Park Natelli Holdings Calvert Planned 300 MW –
Bauxite Data Center 2 Rowan Digital Infrastructure Frederick Planned – 2026
Dickerson Data Center Campus (Atmosphere) Atmosphere Data Centers Frederick Planned – –
Johns Hopkins University - Data Science and Computing Infrastructure Data Center Johns Hopkins University Baltimore Planned – –
TPC Data Centers - Konterra 1 TPC Data Centers Prince George's Planned – 2025
MAG Partners - Baltimore Peninsula Data Center MAG Partners Baltimore Cancelled 50 MW –
Mountain Branch AI Energy Campus Mountain Branch Golf Club Harford Cancelled – –

Local pushback

Bans and moratoriums

19 recorded as enacted, 3 proposed or under review, 0 expired, rejected or lifted (AI GridWatch). A time-limited moratorium with no documented end date keeps showing as enacted; check with the town or county.

WhereLevelStatusDateRuns
Anne Arundel County · Anne Arundel Local Enacted Oct 1, 2026 to Jan 31, 2028
Talbot County · Talbot Local Proposed Sep 8, 2026 Term not documented
Calvert County · Calvert Local Enacted Aug 18, 2026 to Feb 28, 2027
Wicomico County · Wicomico County Enacted Aug 6, 2026 to Aug 6, 2027
Federalsburg · Caroline City Enacted Aug 4, 2026 to Aug 4, 2029
Ridgely · Caroline Local Enacted Aug 1, 2026 to Aug 31, 2027
Queen Anne's County · Queen Anne's Local Enacted Jul 29, 2026 to Jul 29, 2027
Montgomery County · Montgomery Local Enacted Jul 28, 2026 to Jan 28, 2028
Prince George's County · Prince George's Local Enacted Jul 7, 2026 to Jul 7, 2028
Caroline County · Caroline Local Enacted Jul 1, 2026 A stated duration, but the end date isn't recorded here
Washington County · Washington Local Enacted Jun 30, 2026 to Jun 30, 2027
Baltimore City · Baltimore Local Enacted Jun 16, 2026 to Jun 16, 2027
Harford County · Harford Local Enacted Jun 10, 2026 No end date by design — a permanent ban or standing statute
Dorchester County · Dorchester Local Enacted Jun 1, 2026 A stated duration, but the end date isn't recorded here
Howard County · Howard Local Enacted Jun 1, 2026 to Nov 2, 2027

By county

Where the data centers cluster

CountyMapped sitesHours without power a year
Anne Arundel County73.1 h
Baltimore city73.8 h
Frederick County42.6 h
Montgomery County22.8 h
Howard County22.3 h
Baltimore County24.2 h
Prince George's County23.2 h

Every named site

The list

22 of 26 operating sites carry a name or operator; the rest are on the map above only. Area is the mapped outline (land for a campus, roof for a building).

SiteOperatorCountySourceAcres
Lincoln Rackhouse Maryland – Montgomery Building 3.3
TierPoint Baltimore BWI – Anne Arundel Building 0.8
Baltimore Technology Park – Baltimore Building 0.7
Johns Hopkins Data Center – Baltimore Building 0.1
Crown Castle Baltimore – Baltimore Point –
AiNET One Market Center AiNET Baltimore Point –
Expedient Owings Mills Expedient Baltimore Point –
Lumen Baltimore Lumen Baltimore Point –
Expedient Tidepoint Expedient Baltimore Point –
CyberNAP Glen Burnie AiNET Anne Arundel Building –
Aligned Data Centers IAD-04 Aligned Data Centers Frederick Operator's own list –
NASA Center for Climate Simulation (NCCS), Building 28, Goddard Space Flight Center NASA Prince George's Operator's own list –
TierPoint Baltimore (BAL) TierPoint Baltimore Operator's own list –
Amazon Data Services Inc Ltw060 Amazon Web Services Anne Arundel EPA record –
Amazon Data Services Inc Ltw062 Amazon Web Services Anne Arundel EPA record –
Fannie Mae Utc Data Center – Frederick EPA record –
Ibm Annapolis Data Center Ibm Anne Arundel EPA record –
Aligned Data Centers (Md) Propco, Llc - Frederick Md Data Center Campus Aligned Frederick EPA record –
Annapolis Data Center – Anne Arundel EPA record –
Kaiser Permanente Data Center – Montgomery EPA record –
Sidus Group Annapolis Data Center – Anne Arundel Overture place –
Vision Data Center – Baltimore Overture place –

How many data centers are in Maryland?

26 operating or permitted sites on this map, from OpenStreetMap, EPA facility records and other open sources: the 28th most of any state. The map covers most large sites, not every server room, so the true number is higher.

How many data centers are being built in Maryland?

3 under construction and 9 planned or announced in the Civic Returns and Server Country databases; the 7 that publish a size add up to about 3.3 GW. 2 projects have been cancelled.

Which Maryland county has the most data centers?

Anne Arundel County, with 7 operating sites, then Baltimore city (7) and Frederick County (4).

Who operates data centers in Maryland?

Among sites that name an operator: AiNET (2), Expedient (2), Amazon Web Services (2), Lumen (1), Aligned Data Centers (1).

What do Maryland households pay for electricity?

19.5¢ per kWh on average in 2025 (US: 17.2¢), up 47% since 2018, from EIA-861. Prices move with fuel, storms and wires spending as well as new demand.

Sources: operating sites from OpenStreetMap © OpenStreetMap contributors (ODbL 1.0), read Nov 17, 2026; operators' own published facility lists; EPA ECHO facility records (public domain); Civic Returns, US Data Centers & Community Benefits Dataset (CC BY 4.0); Overture Maps places (CDLA-Permissive-2.0); Wikidata (CC0); EIA-860. Projects in development from Civic Returns, the Server Country project database, AI GridWatch and Megawattlas (all CC BY 4.0). Moratoriums from AI GridWatch (CC BY 4.0). AI campuses from Epoch AI, "AI data centers", CC BY 4.0. Electricity prices: EIA-861. Outage hours: ORNL EAGLE-I. How this is counted.