AI data center · Port Washington, Wisconsin

OpenAI Stargate Wisconsin

Oracle's AI campus in Ozaukee County. It is not drawing power yet and is planned to reach 1.30 GW by December 2028.

Power now–As of Jul 24, 2026
Planned peak1.30 GWDecember 2028
Compute–H100-equivalent chips now
Capital cost–So far, 2025 dollars

Latest look · Jul 24, 2026

What the satellite shows

Construction continues, Buildings 1 and 2 appear roughly halfway roofed, and building 3 foundation is halfway done.

Build-out

Power, month by month

0 MW500 MW1 GW1.5 GW202620272028Today
Power drawn by OpenAI Stargate Wisconsin, from Epoch AI's dated observations and (hatched) its projections.
0 MW500 MW1 GW1.5 GW202620272028Today
Power drawn by OpenAI Stargate Wisconsin, from Epoch AI's dated observations and (hatched) its projections.

Who

Owners, users and builders

Owner
Oracle
Used by
OpenAI
Project
Stargate
County
Ozaukee County (approximate)

Where

On the map of Wisconsin

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed at the centre of Port Washington, as no address could be matched, so the dot and the county are approximate.

Nearby

Power plants within 15 miles

PlantSourceCapacityDistance
Port Washington Generating Station● Natural gas1.23 GW0.8 mi
Onion River● Solar150 MW14.9 mi
Jackson Solar WI, LLC● Solar8 MW11.6 mi
Washington County● Solar2 MW14.3 mi

Timeline

Every observation

DateWhat Epoch AI sawPower
Jul 24, 2026Construction continues, Buildings 1 and 2 appear roughly halfway roofed, and building 3 foundation is halfway done.–
Feb 14, 2026Land clearing continues, foundation construction clearly begins for eastern and northern buildings (Building 1-2)–
Jan 2, 2026Ground broken for the facility, land clearing begins for all buildings–

Plus 1 projected step to December 2028, from Epoch AI's reading of the build plans.

How much power does OpenAI Stargate Wisconsin use?

It is not drawing power yet in Epoch AI's timeline; it is planned to reach about 1.30 GW by December 2028.

Who owns OpenAI Stargate Wisconsin?

Oracle; used by OpenAI. Labels in brackets are Epoch AI's confidence where it is not "confident".

How reliable is the power around OpenAI Stargate Wisconsin?

In Ozaukee County, the average customer is without power about 5.5 hours in a typical year in this site's outage record, with 23 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.

What power plants are near OpenAI Stargate Wisconsin?

4 plants within 15 miles total about 1.39 GW; the largest is Port Washington Generating Station (1.23 GW, natural gas), 0.8 miles away. Nearness does not mean it supplies the campus.

Epoch AI's sources for this campus