AI data center · Port Washington, Wisconsin
OpenAI Stargate Wisconsin
Oracle's AI campus in Ozaukee County. It is not drawing power yet and is planned to reach 1.30 GW by December 2028.
Latest look · Jul 24, 2026
What the satellite shows
Construction continues, Buildings 1 and 2 appear roughly halfway roofed, and building 3 foundation is halfway done.
Build-out
Power, month by month
Who
Owners, users and builders
- Owner
- Oracle
- Used by
- OpenAI
- Project
- Stargate
- County
- Ozaukee County (approximate)
Where
On the map of Wisconsin
Placed at the centre of Port Washington, as no address could be matched, so the dot and the county are approximate.
Nearby
Power plants within 15 miles
| Plant | Source | Capacity | Distance |
|---|---|---|---|
| Port Washington Generating Station | ● Natural gas | 1.23 GW | 0.8 mi |
| Onion River | ● Solar | 150 MW | 14.9 mi |
| Jackson Solar WI, LLC | ● Solar | 8 MW | 11.6 mi |
| Washington County | ● Solar | 2 MW | 14.3 mi |
Timeline
Every observation
| Date | What Epoch AI saw | Power |
|---|---|---|
| Jul 24, 2026 | Construction continues, Buildings 1 and 2 appear roughly halfway roofed, and building 3 foundation is halfway done. | – |
| Feb 14, 2026 | Land clearing continues, foundation construction clearly begins for eastern and northern buildings (Building 1-2) | – |
| Jan 2, 2026 | Ground broken for the facility, land clearing begins for all buildings | – |
Plus 1 projected step to December 2028, from Epoch AI's reading of the build plans.
How much power does OpenAI Stargate Wisconsin use?
It is not drawing power yet in Epoch AI's timeline; it is planned to reach about 1.30 GW by December 2028.
Who owns OpenAI Stargate Wisconsin?
Oracle; used by OpenAI. Labels in brackets are Epoch AI's confidence where it is not "confident".
How reliable is the power around OpenAI Stargate Wisconsin?
In Ozaukee County, the average customer is without power about 5.5 hours in a typical year in this site's outage record, with 23 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.
What power plants are near OpenAI Stargate Wisconsin?
4 plants within 15 miles total about 1.39 GW; the largest is Port Washington Generating Station (1.23 GW, natural gas), 0.8 miles away. Nearness does not mean it supplies the campus.
Epoch AI's sources for this campus
Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.