AI data center · Mount Pleasant, Wisconsin
Microsoft Fairwater Wisconsin
Microsoft's AI campus in Racine County. It draws about 369 MW today and is planned to reach 2.71 GW by May 2028.
Latest look · May 15, 2026
What the satellite shows
The main shell of Building 2 looks almost completed. In Area 2 (northwest of Buildings 1-2), the grading for the original design has been replaced with grading for the new 9-building design, making way for Buildings 3-11. Work continues on the northern substation in Area 2.
Build-out
Power, month by month
Who
Owners, users and builders
- Owner
- Microsoft
- Used by
- OpenAI (likely), Microsoft (likely)
- Project
- Microsoft AI WAN
- Energy companies
- WE Energies
- Chips
- B200
- Water use
- 0.01 million gallons a day (Epoch AI estimate)
- Address
- 4800 90th St, Mount Pleasant, WI 53403
- County
- Racine County
Where
On the map of Wisconsin
Placed by its street address.
Nearby
Power plants within 15 miles
| Plant | Source | Capacity | Distance |
|---|---|---|---|
| Elm Road Generating Station | ● Coal | 1.40 GW | 12.4 mi |
| South Oak Creek | ● Coal | 642 MW | 12.3 mi |
| Zion Energy Center | ● Natural gas | 597 MW | 13.6 mi |
| Paris (WI) | ● Natural gas | 382 MW | 6 mi |
| Paris Solar | ● Solar | 310 MW | 6.2 mi |
| Waxdale | ● Biomass | 12 MW | 2.4 mi |
| Pheasant Run Landfill Gas Recovery | ● Biomass | 9 MW | 9.9 mi |
| Caledonia Solar WI, LLC | ● Solar | 6 MW | 9.2 mi |
Timeline
Every observation
| Date | What Epoch AI saw | Power |
|---|---|---|
| May 15, 2026 | The main shell of Building 2 looks almost completed. In Area 2 (northwest of Buildings 1-2), the grading for the original design has been replaced with grading for the new 9-building design, making way for Buildings 3-11. Work continues on the northern substation in Area 2. | 442 MW |
| Apr 16, 2026 | Building 1 is operational. X post from Microsoft saying this date for Fairwater becoming operational. | 442 MW |
| Jan 28, 2026 | Building 1 looks complete, but based on Microsoft announcements, it's not fully operational yet. Steel framing is underway for Building 2. | – |
| Sep 26, 2025 | Building 1 cooling and backup generators all look complete from above but there is still construction visible around the building. Building 2 is well underway with a foundation and a complete substation. Large carpark and concrete area north of Building 2. Building 3 has a concrete foundation and a substation underway. | – |
| Jul 14, 2023 | Land clearing begins for Building 1. | – |
Plus 2 projected steps to May 2028, from Epoch AI's reading of the build plans.
How much power does Microsoft Fairwater Wisconsin use?
About 369 MW as of May 15, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 2.71 GW in its build plans by May 2028. Running all year, 369 MW would use about 3.2 TWh.
Who owns Microsoft Fairwater Wisconsin?
Microsoft; used by OpenAI (likely), Microsoft (likely). Labels in brackets are Epoch AI's confidence where it is not "confident".
How reliable is the power around Microsoft Fairwater Wisconsin?
In Racine County, the average customer is without power about 3.1 hours in a typical year in this site's outage record, with 4 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.
What power plants are near Microsoft Fairwater Wisconsin?
8 plants within 15 miles total about 3.39 GW; the largest is Elm Road Generating Station (1.40 GW, coal), 12.4 miles away. Nearness does not mean it supplies the campus.
Epoch AI's sources for this campus
- Microsoft blog with engineering details
- Microsoft blog with more general information
- Construction Permit Application for building 1
- Plan for 9-building and 6-building expansions
- OpenAI article mentioning they use Microsoft's Fairwater supercomputers