AI data center · Eagle Mountain, Utah

QTS Eagle Mountain

Meta's AI campus in Utah County. It is not drawing power yet and is planned to reach 411 MW by July 2027.

Power now–As of May 2, 2026
Planned peak411 MWJuly 2027
Compute–H100-equivalent chips now
Capital cost–So far, 2025 dollars

Latest look · May 2, 2026

What the satellite shows

Building 1 roof finished. Satellite imagery shows construction vehicles and concrete pads with no air cooled chiller units indicating Buildings 1 and 2 cooling install continues. On the other side of each building, emergency generator install continues as well.

Build-out

Power, month by month

0 MW100 MW200 MW300 MW400 MW500 MW2024202520262027Today
Power drawn by QTS Eagle Mountain, from Epoch AI's dated observations and (hatched) its projections.
0 MW100 MW200 MW300 MW400 MW500 MW2024202520262027Today
Power drawn by QTS Eagle Mountain, from Epoch AI's dated observations and (hatched) its projections.

Who

Owners, users and builders

Owner
Meta (speculative)
Used by
Meta (speculative)
Chips
B300
Address
652 E Hyperscale Way, Eagle Mountain, UT 84013
County
Utah County

Where

On the map of Utah

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed by its street address.

Nearby

Power plants within 15 miles

PlantSourceCapacityDistance
Faraday Solar● Solar525 MW12.4 mi
Faraday Energy Storage● Storage150 MW13 mi

Timeline

Every observation

DateWhat Epoch AI sawPower
May 2, 2026Building 1 roof finished. Satellite imagery shows construction vehicles and concrete pads with no air cooled chiller units indicating Buildings 1 and 2 cooling install continues. On the other side of each building, emergency generator install continues as well.–
Sep 8, 2025Site preparation continues. Outline of a first building that is not the data center of interest Buildings 1 or 2 is visible.–
Oct 1, 2023First signs of site preparation show up on satellite imagery.–

Plus 2 projected steps to July 2027, from Epoch AI's reading of the build plans.

How much power does QTS Eagle Mountain use?

It is not drawing power yet in Epoch AI's timeline; it is planned to reach about 411 MW by July 2027.

Who owns QTS Eagle Mountain?

Meta (speculative); used by Meta (speculative). Labels in brackets are Epoch AI's confidence where it is not "confident".

How reliable is the power around QTS Eagle Mountain?

In Utah County, the average customer is without power about 1.5 hours in a typical year in this site's outage record, with 0 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.

What power plants are near QTS Eagle Mountain?

2 plants within 15 miles total about 675 MW; the largest is Faraday Solar (525 MW, solar), 12.4 miles away. Nearness does not mean it supplies the campus.

Epoch AI's sources for this campus

Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.