Storage power plant · Utah, UT

Faraday Energy Storage

Faraday Energy Storage is a 150 MW storage power plant in Utah County, Utah, operated by Lydian Energy. Its oldest generator still running came online in 2026.

Capacity150 MWNameplate, September 2026
Net energy–Not reported
Capacity factor–Not a full year of data
Generators1Oldest from 2026

Faraday Energy Storage in context

Among the 7 storage plants in Utah in the EIA's inventory, it is the 3rd largest, about 10% of the state's 1.5 GW of storage capacity.

Utah County has 12 power plants of 1 MW or more with 2.2 GW in all; Faraday Energy Storage is 7% of that.

The average electricity customer in Utah County goes 1.5 hours a year without power, the 22nd most of 23 counties in Utah. The county's page has the full outage record.

Where it is

Faraday Energy Storage (outlined) and other plants in Utah County, shaded. 40.082, -112.069.

Plant facts

Operator
Lydian Energy
Sector
IPP Non-CHP
Grid operator
PACE
County
Utah County, UT
EIA plant ID
69424
Where Utah's power comes from → Utah power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
FBS1 Batteries 150 MW · 600 MWh 2026 –

Questions

Faraday Energy Storage, answered

How much can Faraday Energy Storage store and deliver?

Faraday Energy Storage can deliver up to 150 MW and hold 600 MWh of energy, from one battery or storage system.

Where is Faraday Energy Storage?

Faraday Energy Storage is in Utah County, Utah, at about 40.082°, -112.069°. It is one of 12 power plants of 1 MW or more in the county. The average electricity customer in Utah County goes 1.5 hours a year without power, the 22nd most of 23 counties in Utah. The county's page has the full outage record.

Who operates Faraday Energy Storage?

It is operated by Lydian Energy (EIA sector: IPP Non-CHP), and it feeds PacifiCorp East.

When did Faraday Energy Storage open?

Its oldest generator still running came online in 2026.