AI data center · Vineland, New Jersey

Microsoft-Nebius New Jersey

Nebius's AI campus in Cumberland County. It draws about 50 MW today and is planned to reach 70 MW by April 2026.

Power now50 MWAs of Jul 12, 2026
Planned peak70 MWApril 2026
Compute57kH100-equivalent chips now
Capital cost$1.9BSo far, 2025 dollars

Latest look · Jul 12, 2026

What the satellite shows

Compared with the April 2026 image, the building shell is closer to completion, and several additional air-cooled chillers have appeared on the ground, though they do not yet appear to be connected or operating. We therefore keep IT capacity at 50 MW.

Build-out

Power, month by month

0 MW20 MW40 MW60 MW80 MW20252026
Power drawn by Microsoft-Nebius New Jersey, from Epoch AI's dated observations.
0 MW20 MW40 MW60 MW80 MW20252026
Power drawn by Microsoft-Nebius New Jersey, from Epoch AI's dated observations.

Who

Owners, users and builders

Owner
Nebius
Used by
Microsoft (likely)
Chips
B300
Address
3963 S Lincoln Ave, Vineland, New Jersey
County
Cumberland County

Where

On the map of New Jersey

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed by its street address.

Nearby

Power plants within 15 miles

PlantSourceCapacityDistance
Cumberland (NJ)● Natural gas231 MW4.6 mi
Sherman Avenue● Natural gas113 MW2.6 mi
Clayville● Natural gas73 MW0.3 mi
Howard Down● Natural gas68 MW4.3 mi
Vineland Solar LLC● Solar15 MW3.7 mi
NJ Oak Solar Plant● Solar10 MW9.6 mi
Seabrook Solar Plant● Solar7 MW11.2 mi
Cedar Branch● Solar6 MW5.9 mi

Timeline

Every observation

DateWhat Epoch AI sawPower
Jul 12, 2026Compared with the April 2026 image, the building shell is closer to completion, and several additional air-cooled chillers have appeared on the ground, though they do not yet appear to be connected or operating. We therefore keep IT capacity at 50 MW.70 MW
Apr 15, 2026High-resolution satellite imagery shows the air-cooled chiller array has grown to roughly 30 units, enough to support the first phase. We estimate Building 1 became operational around early 2026 with about 50 MW of IT capacity (70 MW total facility power at a 1.4 PUE), based on DataOne's disclosure of a first 50 MW phase. SemiAnalysis estimated the full 50 MW was reached around January to February 2026 (SemiAnalysis); this April image is our first high-resolution confirmation that the cooling is in place.70 MW
Dec 15, 2025By mid-December 2025 the building was still not complete. A satellite analysis by SemiAnalysis found that the air-cooled chillers serving the second half of the first 50 MW phase were not yet installed, so the phase was not yet operational. SemiAnalysis estimated the full 50 MW would be reached around January to February 2026.–
May 31, 2024Land clearing begins for northern two buildings (Building 1-2).–

How much power does Microsoft-Nebius New Jersey use?

About 50 MW as of Jul 12, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 70 MW in its build plans by April 2026. Running all year, 50 MW would use about 0.4 TWh.

Who owns Microsoft-Nebius New Jersey?

Nebius; used by Microsoft (likely). Labels in brackets are Epoch AI's confidence where it is not "confident".

How reliable is the power around Microsoft-Nebius New Jersey?

In Cumberland County, the average customer is without power about 2.8 hours in a typical year in this site's outage record, with 2 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.

What power plants are near Microsoft-Nebius New Jersey?

8 plants within 15 miles total about 567 MW; the largest is Cumberland (NJ) (231 MW, natural gas), 4.6 miles away. Nearness does not mean it supplies the campus.

Epoch AI's sources for this campus

Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.