AI data center · Vineland, New Jersey
Microsoft-Nebius New Jersey
Nebius's AI campus in Cumberland County. It draws about 50 MW today and is planned to reach 70 MW by April 2026.
Latest look · Jul 12, 2026
What the satellite shows
Compared with the April 2026 image, the building shell is closer to completion, and several additional air-cooled chillers have appeared on the ground, though they do not yet appear to be connected or operating. We therefore keep IT capacity at 50 MW.
Build-out
Power, month by month
Who
Owners, users and builders
- Owner
- Nebius
- Used by
- Microsoft (likely)
- Chips
- B300
- Address
- 3963 S Lincoln Ave, Vineland, New Jersey
- County
- Cumberland County
Where
On the map of New Jersey
Placed by its street address.
Nearby
Power plants within 15 miles
| Plant | Source | Capacity | Distance |
|---|---|---|---|
| Cumberland (NJ) | ● Natural gas | 231 MW | 4.6 mi |
| Sherman Avenue | ● Natural gas | 113 MW | 2.6 mi |
| Clayville | ● Natural gas | 73 MW | 0.3 mi |
| Howard Down | ● Natural gas | 68 MW | 4.3 mi |
| Vineland Solar LLC | ● Solar | 15 MW | 3.7 mi |
| NJ Oak Solar Plant | ● Solar | 10 MW | 9.6 mi |
| Seabrook Solar Plant | ● Solar | 7 MW | 11.2 mi |
| Cedar Branch | ● Solar | 6 MW | 5.9 mi |
Timeline
Every observation
| Date | What Epoch AI saw | Power |
|---|---|---|
| Jul 12, 2026 | Compared with the April 2026 image, the building shell is closer to completion, and several additional air-cooled chillers have appeared on the ground, though they do not yet appear to be connected or operating. We therefore keep IT capacity at 50 MW. | 70 MW |
| Apr 15, 2026 | High-resolution satellite imagery shows the air-cooled chiller array has grown to roughly 30 units, enough to support the first phase. We estimate Building 1 became operational around early 2026 with about 50 MW of IT capacity (70 MW total facility power at a 1.4 PUE), based on DataOne's disclosure of a first 50 MW phase. SemiAnalysis estimated the full 50 MW was reached around January to February 2026 (SemiAnalysis); this April image is our first high-resolution confirmation that the cooling is in place. | 70 MW |
| Dec 15, 2025 | By mid-December 2025 the building was still not complete. A satellite analysis by SemiAnalysis found that the air-cooled chillers serving the second half of the first 50 MW phase were not yet installed, so the phase was not yet operational. SemiAnalysis estimated the full 50 MW would be reached around January to February 2026. | – |
| May 31, 2024 | Land clearing begins for northern two buildings (Building 1-2). | – |
How much power does Microsoft-Nebius New Jersey use?
About 50 MW as of Jul 12, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 70 MW in its build plans by April 2026. Running all year, 50 MW would use about 0.4 TWh.
Who owns Microsoft-Nebius New Jersey?
Nebius; used by Microsoft (likely). Labels in brackets are Epoch AI's confidence where it is not "confident".
How reliable is the power around Microsoft-Nebius New Jersey?
In Cumberland County, the average customer is without power about 2.8 hours in a typical year in this site's outage record, with 2 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.
What power plants are near Microsoft-Nebius New Jersey?
8 plants within 15 miles total about 567 MW; the largest is Cumberland (NJ) (231 MW, natural gas), 4.6 miles away. Nearness does not mean it supplies the campus.
Epoch AI's sources for this campus
- Nebius: up to 300 MW capacity at new New Jersey data center
- DataOne and Nebius partner for 300 MW AI data center (Data Centre Magazine)
- Microsoft secures 100,000 NVIDIA GB300 via Nebius deal (Tom's Hardware)
- DataOne CEO on first 50 MW delivery to Nebius (LinkedIn)
- Large data center nears completion in Vineland (Cape May County Herald)
- SemiAnalysis: Stop Saying Half of 2026 US Datacenter Capacity Is Canceled
Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.