Google's AI campus in Sarpy County. It draws about 237 MW today and is planned to reach 284 MW by August 2024.
Latest look · May 4, 2026
What the satellite shows
Building 4 shell mostly complete, Building 5 steel framing is underway.
Build-out
Power, month by month
Who
Owners, users and builders
- Owner
- Used by
- Google DeepMind (speculative)
- Investors
- Chips
- TPU v4, TPU v5e, TPU v5p
- Water use
- 0.09 million gallons a day (Epoch AI estimate)
- Address
- 14651-15249 Gold Coast Rd 68138 Papillion Nebraska, USA
- County
- Sarpy County (approximate)
Where
On the map of Nebraska
Placed at the centre of Papillion, as no address could be matched, so the dot and the county are approximate.
Nearby
Power plants within 15 miles
| Plant | Source | Capacity | Distance |
|---|---|---|---|
| Walter Scott Jr Energy Center | ● Coal | 1.65 GW | 12.6 mi |
| North Omaha | ● Coal | 645 MW | 14.6 mi |
| Turtle Creek | ● Natural gas | 528 MW | 5.9 mi |
| Cass County | ● Natural gas | 345 MW | 14.8 mi |
| Sarpy County | ● Natural gas | 338 MW | 5.9 mi |
| Standing Bear Lake | ● Natural gas | 163 MW | 12 mi |
| Jones Street | ● Oil | 130 MW | 11 mi |
| Missouri River Wastewater Treatment | ● Biomass | 3 MW | 8.8 mi |
Timeline
Every observation
| Date | What Epoch AI saw | Power |
|---|---|---|
| May 4, 2026 | Building 4 shell mostly complete, Building 5 steel framing is underway. | 284 MW |
| Nov 3, 2025 | Land cleared for Building 4 and 5. | 284 MW |
| Aug 3, 2024 | Building 3 looks operational. | 284 MW |
| Feb 15, 2024 | Building 2 assumed operational due to vapor from cooling towers. Building 3 5/7 cooling towers installed. | 95 MW |
| Jan 23, 2023 | Building 1 assumed operational due to vapor from cooling towers. Building 2 4/7 cooling towers installed. Building 3 roof complete coverage but unfinished. | 95 MW |
| Oct 16, 2022 | Building 2 under construction. Building 3 begins construction. | – |
| Mar 4, 2020 | Land clearing begins for Building 1 of expansion. | – |
How much power does Google Papillion use?
About 237 MW as of May 4, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 284 MW in its build plans by August 2024. Running all year, 237 MW would use about 2.1 TWh.
Who owns Google Papillion?
Google; used by Google DeepMind (speculative). Investors: Google. Labels in brackets are Epoch AI's confidence where it is not "confident".
How reliable is the power around Google Papillion?
In Sarpy County, the average customer is without power about 6.5 hours in a typical year in this site's outage record, with 8 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.
What power plants are near Google Papillion?
8 plants within 15 miles total about 3.80 GW; the largest is Walter Scott Jr Energy Center (1.65 GW, coal), 12.6 miles away. Nearness does not mean it supplies the campus.