AI data center · Lincoln, Nebraska
Google Lincoln
Google's AI campus in Lancaster County. It draws about 141 MW today and is planned to reach 339 MW by October 2027.
Latest look · May 12, 2026
What the satellite shows
Building 1 operational. This is based on the fact that is no more visible equipment or construction around the building, and based on previous imagery and when construction started on the last pieces of equipment (fans). Building 2's roof is complete, with generator construction more than halfway complete and cooling construction beginning. Electrical equipment on the side of Building 2 is also around halfway complete.
Build-out
Power, month by month
Who
Owners, users and builders
- Owner
- Chips
- TPU v6e, TPU v7
- Address
- 5475 Cloud Ct, Lincoln, NE 68514
- County
- Lancaster County
Where
On the map of Nebraska
Placed by its street address.
Nearby
Power plants within 15 miles
| Plant | Source | Capacity | Distance |
|---|---|---|---|
| Rokeby | ● Natural gas | 266 MW | 13 mi |
| Terry Bundy Generating Station | ● Natural gas | 216 MW | 1.7 mi |
| J Street | ● Natural gas | 27 MW | 7.7 mi |
| Archer Daniels Midland Lincoln | ● Natural gas | 8 MW | 3.3 mi |
| Holdrege Solar Center | ● Solar | 4 MW | 10.8 mi |
| 2nd & N BESS | ● Storage | 3 MW | 7.6 mi |
Timeline
Every observation
| Date | What Epoch AI saw | Power |
|---|---|---|
| May 12, 2026 | Building 1 operational. This is based on the fact that is no more visible equipment or construction around the building, and based on previous imagery and when construction started on the last pieces of equipment (fans). Building 2's roof is complete, with generator construction more than halfway complete and cooling construction beginning. Electrical equipment on the side of Building 2 is also around halfway complete. | 170 MW |
| Oct 23, 2025 | Building 1 looks mostly complete: the large items like generators and substation are done. It is just missing 2 more cooling towers (4 fans). They just seem to be paving and setting up the secondary equipment so it is probably a few months away from operation. Building 2 foundation has been laid. | – |
| Jun 1, 2023 | Land clearing begins. | – |
Plus 1 projected step to October 2027, from Epoch AI's reading of the build plans.
How much power does Google Lincoln use?
About 141 MW as of May 12, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 339 MW in its build plans by October 2027. Running all year, 141 MW would use about 1.2 TWh.
Who owns Google Lincoln?
Google. Labels in brackets are Epoch AI's confidence where it is not "confident".
How reliable is the power around Google Lincoln?
In Lancaster County, the average customer is without power about 0.5 hours in a typical year in this site's outage record, with 0 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.
What power plants are near Google Lincoln?
6 plants within 15 miles total about 524 MW; the largest is Rokeby (266 MW, natural gas), 13 miles away. Nearness does not mean it supplies the campus.
Epoch AI's sources for this campus
- Army corps land use application with a useful construction plan diagram, split across 7 phases
- DCD article on the start of site construction
- Rezoning approval, stating 75 ft building height
Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.