AI data center · Lincoln, Nebraska

Google Lincoln

Google's AI campus in Lancaster County. It draws about 141 MW today and is planned to reach 339 MW by October 2027.

Power now141 MWAs of May 12, 2026
Planned peak339 MWOctober 2027
Compute198kH100-equivalent chips now
Capital cost$5.3BSo far, 2025 dollars

Latest look · May 12, 2026

What the satellite shows

Building 1 operational. This is based on the fact that is no more visible equipment or construction around the building, and based on previous imagery and when construction started on the last pieces of equipment (fans). Building 2's roof is complete, with generator construction more than halfway complete and cooling construction beginning. Electrical equipment on the side of Building 2 is also around halfway complete.

Build-out

Power, month by month

0 MW100 MW200 MW300 MW400 MW2024202520262027Today
Power drawn by Google Lincoln, from Epoch AI's dated observations and (hatched) its projections.
0 MW100 MW200 MW300 MW400 MW2024202520262027Today
Power drawn by Google Lincoln, from Epoch AI's dated observations and (hatched) its projections.

Who

Owners, users and builders

Owner
Google
Chips
TPU v6e, TPU v7
Address
5475 Cloud Ct, Lincoln, NE 68514
County
Lancaster County

Where

On the map of Nebraska

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed by its street address.

Nearby

Power plants within 15 miles

PlantSourceCapacityDistance
Rokeby● Natural gas266 MW13 mi
Terry Bundy Generating Station● Natural gas216 MW1.7 mi
J Street● Natural gas27 MW7.7 mi
Archer Daniels Midland Lincoln● Natural gas8 MW3.3 mi
Holdrege Solar Center● Solar4 MW10.8 mi
2nd & N BESS● Storage3 MW7.6 mi

Timeline

Every observation

DateWhat Epoch AI sawPower
May 12, 2026Building 1 operational. This is based on the fact that is no more visible equipment or construction around the building, and based on previous imagery and when construction started on the last pieces of equipment (fans). Building 2's roof is complete, with generator construction more than halfway complete and cooling construction beginning. Electrical equipment on the side of Building 2 is also around halfway complete.170 MW
Oct 23, 2025Building 1 looks mostly complete: the large items like generators and substation are done. It is just missing 2 more cooling towers (4 fans). They just seem to be paving and setting up the secondary equipment so it is probably a few months away from operation. Building 2 foundation has been laid.–
Jun 1, 2023Land clearing begins.–

Plus 1 projected step to October 2027, from Epoch AI's reading of the build plans.

How much power does Google Lincoln use?

About 141 MW as of May 12, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 339 MW in its build plans by October 2027. Running all year, 141 MW would use about 1.2 TWh.

Who owns Google Lincoln?

Google. Labels in brackets are Epoch AI's confidence where it is not "confident".

How reliable is the power around Google Lincoln?

In Lancaster County, the average customer is without power about 0.5 hours in a typical year in this site's outage record, with 0 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.

What power plants are near Google Lincoln?

6 plants within 15 miles total about 524 MW; the largest is Rokeby (266 MW, natural gas), 13 miles away. Nearness does not mean it supplies the campus.

Epoch AI's sources for this campus

Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.