AI data center · Omaha, Nebraska
Google Omaha
Google's AI campus in Douglas County. It draws about 237 MW today and is planned to reach 474 MW by July 2028.
Latest look · Jun 30, 2026
What the satellite shows
Building 3 is operational (estimate). Based on there being minimal construction work as of May 15.
Build-out
Power, month by month
Who
Owners, users and builders
- Owner
- Used by
- Google DeepMind (speculative)
- Chips
- TPU v5e, TPU v5p, TPU v6e, TPU v7
- Water use
- 0.09 million gallons a day (Epoch AI estimate)
- Address
- 11110 State St, Omaha, NE 68142
- County
- Douglas County
Where
On the map of Nebraska
Placed by its street address.
Nearby
Power plants within 15 miles
| Plant | Source | Capacity | Distance |
|---|---|---|---|
| North Omaha | ● Coal | 645 MW | 7.5 mi |
| Sarpy County | ● Natural gas | 338 MW | 12.9 mi |
| Standing Bear Lake | ● Natural gas | 163 MW | 1.4 mi |
| Jones Street | ● Oil | 130 MW | 10.4 mi |
| Fort Calhoun Community Solar | ● Solar | 5 MW | 9.4 mi |
| Missouri River Wastewater Treatment | ● Biomass | 3 MW | 12.3 mi |
Timeline
Every observation
| Date | What Epoch AI saw | Power |
|---|---|---|
| Jun 30, 2026 | Building 3 is operational (estimate). Based on there being minimal construction work as of May 15. | 284 MW |
| May 15, 2026 | Building 3 appears almost complete, with only minimal construction work and equipment remaining. The cooling towers are spaced apart in an unusual way, but there's no obvious sign that more will be installed before operation. Buildings 4 and 5 haven't started construction yet, the cleared land is still empty. | 189 MW |
| Oct 21, 2025 | Building 3 has all backup generators in place but they are still being installed. Two cooling towers have fans on them, with more underway. To the south of Building 3, more land has been cleared and there's a new carpark. This suggests another building will soon start construction. | 189 MW |
| Apr 21, 2025 | Confident that Building 2 is operational | 189 MW |
| Mar 16, 2025 | Confirmation that there's no obvious construction happening for Building 2. Building 3 roof started. | 189 MW |
| Nov 19, 2024 | Building 2 is operational, based on it being 8 months since the roof was complete, and surrounding infrastructure looks just completed (finishing the cooling towers). | 189 MW |
| Jul 29, 2024 | Building 2 has 3 cooling towers installed. | 95 MW |
| Apr 8, 2024 | Building 1 operational, based on it being 6 months after roof was complete, infrastructure looked complete for 5 months. | 95 MW |
| Nov 25, 2021 | Land clearing begins. | – |
Plus 2 projected steps to July 2028, from Epoch AI's reading of the build plans.
How much power does Google Omaha use?
About 237 MW as of Jun 30, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 474 MW in its build plans by July 2028. Running all year, 237 MW would use about 2.1 TWh.
Who owns Google Omaha?
Google; used by Google DeepMind (speculative). Labels in brackets are Epoch AI's confidence where it is not "confident".
How reliable is the power around Google Omaha?
In Douglas County, the average customer is without power about 8.6 hours in a typical year in this site's outage record, with 6 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.
What power plants are near Google Omaha?
6 plants within 15 miles total about 1.28 GW; the largest is North Omaha (645 MW, coal), 7.5 miles away. Nearness does not mean it supplies the campus.
Epoch AI's sources for this campus
Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.