AI data center · Omaha, Nebraska

Google Omaha

Google's AI campus in Douglas County. It draws about 237 MW today and is planned to reach 474 MW by July 2028.

Power now237 MWAs of Jun 30, 2026
Planned peak474 MWJuly 2028
Compute199kH100-equivalent chips now
Capital cost$9.0BSo far, 2025 dollars

Latest look · Jun 30, 2026

What the satellite shows

Building 3 is operational (estimate). Based on there being minimal construction work as of May 15.

Build-out

Power, month by month

0 MW200 MW400 MW600 MW2022202320242025202620272028Today
Power drawn by Google Omaha, from Epoch AI's dated observations and (hatched) its projections.
0 MW200 MW400 MW600 MW2022202420262028Today
Power drawn by Google Omaha, from Epoch AI's dated observations and (hatched) its projections.

Who

Owners, users and builders

Owner
Google
Used by
Google DeepMind (speculative)
Chips
TPU v5e, TPU v5p, TPU v6e, TPU v7
Water use
0.09 million gallons a day (Epoch AI estimate)
Address
11110 State St, Omaha, NE 68142
County
Douglas County

Where

On the map of Nebraska

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed by its street address.

Nearby

Power plants within 15 miles

PlantSourceCapacityDistance
North Omaha● Coal645 MW7.5 mi
Sarpy County● Natural gas338 MW12.9 mi
Standing Bear Lake● Natural gas163 MW1.4 mi
Jones Street● Oil130 MW10.4 mi
Fort Calhoun Community Solar● Solar5 MW9.4 mi
Missouri River Wastewater Treatment● Biomass3 MW12.3 mi

Timeline

Every observation

DateWhat Epoch AI sawPower
Jun 30, 2026Building 3 is operational (estimate). Based on there being minimal construction work as of May 15.284 MW
May 15, 2026Building 3 appears almost complete, with only minimal construction work and equipment remaining. The cooling towers are spaced apart in an unusual way, but there's no obvious sign that more will be installed before operation. Buildings 4 and 5 haven't started construction yet, the cleared land is still empty.189 MW
Oct 21, 2025Building 3 has all backup generators in place but they are still being installed. Two cooling towers have fans on them, with more underway. To the south of Building 3, more land has been cleared and there's a new carpark. This suggests another building will soon start construction.189 MW
Apr 21, 2025Confident that Building 2 is operational189 MW
Mar 16, 2025Confirmation that there's no obvious construction happening for Building 2. Building 3 roof started.189 MW
Nov 19, 2024Building 2 is operational, based on it being 8 months since the roof was complete, and surrounding infrastructure looks just completed (finishing the cooling towers).189 MW
Jul 29, 2024Building 2 has 3 cooling towers installed.95 MW
Apr 8, 2024Building 1 operational, based on it being 6 months after roof was complete, infrastructure looked complete for 5 months.95 MW
Nov 25, 2021Land clearing begins.–

Plus 2 projected steps to July 2028, from Epoch AI's reading of the build plans.

How much power does Google Omaha use?

About 237 MW as of Jun 30, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 474 MW in its build plans by July 2028. Running all year, 237 MW would use about 2.1 TWh.

Who owns Google Omaha?

Google; used by Google DeepMind (speculative). Labels in brackets are Epoch AI's confidence where it is not "confident".

How reliable is the power around Google Omaha?

In Douglas County, the average customer is without power about 8.6 hours in a typical year in this site's outage record, with 6 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.

What power plants are near Google Omaha?

6 plants within 15 miles total about 1.28 GW; the largest is North Omaha (645 MW, coal), 7.5 miles away. Nearness does not mean it supplies the campus.

Epoch AI's sources for this campus

Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.