AI data center · Kansas City, Missouri
Google Kansas City East
Google's AI campus in Jackson County. It draws about 105 MW today and is planned to reach 126 MW by August 2026.
Latest look · Aug 1, 2026
What the satellite shows
Building 1 operational. Estimated based on present construction progress and typical timelines.
Build-out
Power, month by month
Who
Owners, users and builders
- Owner
- County
- Jackson County (approximate)
Where
On the map of Missouri
Placed at the centre of Kansas City, as no address could be matched, so the dot and the county are approximate.
Nearby
Power plants within 15 miles
| Plant | Source | Capacity | Distance |
|---|---|---|---|
| Hawthorn | ● Coal | 1.05 GW | 3.9 mi |
| Northeast (MO) | ● Oil | 540 MW | 0.6 mi |
| Nearman Creek | ● Coal | 365 MW | 8.4 mi |
| Quindaro | ● Oil | 144 MW | 5 mi |
| Station H | ● Natural gas | 43 MW | 9.2 mi |
| Station I | ● Oil | 38 MW | 9.7 mi |
| Jackson Square | ● Oil | 36 MW | 7.7 mi |
| Hawthorn Solar I | ● Solar | 10 MW | 3.5 mi |
Timeline
Every observation
| Date | What Epoch AI saw | Power |
|---|---|---|
| Aug 1, 2026 | Building 1 operational. Estimated based on present construction progress and typical timelines. | 126 MW |
| Apr 16, 2026 | Building 1 is almost complete, with only cooling needing 4 more fans. Building 2 backup generator construction has begun, and cooling tower installation is about halfway complete. Building 3's roof is almost complete, and construction has started on generators and cooling. A clear foundation has been cleared for Building 4, though no construction has begun. | – |
| Nov 1, 2025 | Foundation work begins for Building 4. Building 2 roof is almost complete, and construction appears to have started on cooling. Building 1 cooling construction continues, and the substation right next to it seems finished as well. | – |
| Jul 1, 2025 | Foundation work begins for Building 3. Building 1 generators seem complete. | – |
| Oct 1, 2024 | Foundation work begins on Building 2. Building 1 roof is fully black. | – |
| Mar 1, 2024 | Foundation work begins on Building 1 | – |
| Dec 1, 2023 | Land clearing begins. | – |
How much power does Google Kansas City East use?
About 105 MW as of Aug 1, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 126 MW in its build plans by August 2026. Running all year, 105 MW would use about 0.9 TWh.
Who owns Google Kansas City East?
Google. Labels in brackets are Epoch AI's confidence where it is not "confident".
How reliable is the power around Google Kansas City East?
In Jackson County, the average customer is without power about 8.0 hours in a typical year in this site's outage record, with 8 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.
What power plants are near Google Kansas City East?
8 plants within 15 miles total about 2.23 GW; the largest is Hawthorn (1.05 GW, coal), 3.9 miles away. Nearness does not mean it supplies the campus.
Epoch AI's sources for this campus
Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.