AI data center · Kansas City, Missouri

Google Kansas City East

Google's AI campus in Jackson County. It draws about 105 MW today and is planned to reach 126 MW by August 2026.

Power now105 MWAs of Aug 1, 2026
Planned peak126 MWAugust 2026
Compute203kH100-equivalent chips now
Capital cost$4.0BSo far, 2025 dollars

Latest look · Aug 1, 2026

What the satellite shows

Building 1 operational. Estimated based on present construction progress and typical timelines.

Build-out

Power, month by month

0 MW50 MW100 MW150 MW202420252026
Power drawn by Google Kansas City East, from Epoch AI's dated observations.
0 MW50 MW100 MW150 MW202420252026
Power drawn by Google Kansas City East, from Epoch AI's dated observations.

Who

Owners, users and builders

Owner
Google
County
Jackson County (approximate)

Where

On the map of Missouri

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed at the centre of Kansas City, as no address could be matched, so the dot and the county are approximate.

Nearby

Power plants within 15 miles

PlantSourceCapacityDistance
Hawthorn● Coal1.05 GW3.9 mi
Northeast (MO)● Oil540 MW0.6 mi
Nearman Creek● Coal365 MW8.4 mi
Quindaro● Oil144 MW5 mi
Station H● Natural gas43 MW9.2 mi
Station I● Oil38 MW9.7 mi
Jackson Square● Oil36 MW7.7 mi
Hawthorn Solar I● Solar10 MW3.5 mi

Timeline

Every observation

DateWhat Epoch AI sawPower
Aug 1, 2026Building 1 operational. Estimated based on present construction progress and typical timelines.126 MW
Apr 16, 2026Building 1 is almost complete, with only cooling needing 4 more fans. Building 2 backup generator construction has begun, and cooling tower installation is about halfway complete. Building 3's roof is almost complete, and construction has started on generators and cooling. A clear foundation has been cleared for Building 4, though no construction has begun.–
Nov 1, 2025Foundation work begins for Building 4. Building 2 roof is almost complete, and construction appears to have started on cooling. Building 1 cooling construction continues, and the substation right next to it seems finished as well.–
Jul 1, 2025Foundation work begins for Building 3. Building 1 generators seem complete.–
Oct 1, 2024Foundation work begins on Building 2. Building 1 roof is fully black.–
Mar 1, 2024Foundation work begins on Building 1–
Dec 1, 2023Land clearing begins.–

How much power does Google Kansas City East use?

About 105 MW as of Aug 1, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 126 MW in its build plans by August 2026. Running all year, 105 MW would use about 0.9 TWh.

Who owns Google Kansas City East?

Google. Labels in brackets are Epoch AI's confidence where it is not "confident".

How reliable is the power around Google Kansas City East?

In Jackson County, the average customer is without power about 8.0 hours in a typical year in this site's outage record, with 8 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.

What power plants are near Google Kansas City East?

8 plants within 15 miles total about 2.23 GW; the largest is Hawthorn (1.05 GW, coal), 3.9 miles away. Nearness does not mean it supplies the campus.

Epoch AI's sources for this campus

Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.