AI data center · Memphis, Tennessee
Colossus 1
SpaceXAI's AI campus in Shelby County. It draws about 340 MW today and is planned to reach 442 MW by July 2025.
Latest look · Jun 15, 2026
What the satellite shows
No major changes to the data center since February. Solar panels have been placed next to the facility.
Build-out
Power, month by month
Who
Owners, users and builders
- Owner
- SpaceXAI
- Used by
- Anthropic
- Energy companies
- MLGW
- Chips
- H100, H200, B200
- Address
- 3231 Riverport Rd, Memphis, TN 38109
- County
- Shelby County
Where
On the map of Tennessee
Placed by its street address.
Nearby
Power plants within 15 miles
| Plant | Source | Capacity | Distance |
|---|---|---|---|
| Allen | ● Natural gas | 1.29 GW | 4.3 mi |
| TVA Southaven Combined Cycle | ● Natural gas | 904 MW | 6.7 mi |
| West Memphis Solar Station | ● Solar | 180 MW | 14.3 mi |
| Wildflower Solar, LLC (MS) | ● Solar | 100 MW | 10.6 mi |
Timeline
Every observation
| Date | What Epoch AI saw | Power |
|---|---|---|
| Jun 15, 2026 | No major changes to the data center since February. Solar panels have been placed next to the facility. | 425 MW |
| Jun 1, 2026 | We assume that Anthropic has started using Colossus 1 now, since the announcement said they would get access to 300 MW "within the month" of May. | 425 MW |
| May 6, 2026 | Anthropic announces their agreement with SpaceX to use all of the compute capacity at Colossus 1. They state that this corresponds to more than 300 MW (presumably IT power) and over 220,000 GPUs. This is slightly different to previous reports adding up to 230,000 GPUs, but still roughly consistent with our estimates. | 425 MW |
| Feb 11, 2026 | All air-cooled chillers have been disconnected and/or removed from the site, leaving only the cooling towers for cooling. The third substation looks complete, with red cables connected to the building. | 425 MW |
| Nov 7, 2025 | Third substation was expected to power the building in Fall. | 442 MW |
| Oct 19, 2025 | There is still construction visible in the third substation yard and next to the new cooling towers. | 348 MW |
| Sep 17, 2025 | Third substation looks completed, but it doesn't appear to be connected to the building yet. Some air-cooled chillers removed, while large cooling towers are added. | 348 MW |
| Jul 22, 2025 | 30k B200s added (in GB200 configuration). | 442 MW |
| Mar 6, 2025 | Second substation almost connected (red cables) | 361 MW |
| Feb 17, 2025 | 150k H100s and 50k H200s online. This is roughly when Musk said, plus on this date they reported "running jobs with 150K+ GPUs". | 361 MW |
| Sep 2, 2024 | 100k H100s online. | 181 MW |
| Aug 11, 2024 | First significant/useful training workload on 25k H100s. | 45 MW |
| Apr 24, 2024 | Construction starts with a road added on site, retrofitting a former Electrolux building. | – |
How much power does Colossus 1 use?
About 340 MW as of Jun 15, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 442 MW in its build plans by July 2025. Running all year, 340 MW would use about 3.0 TWh.
Who owns Colossus 1?
SpaceXAI; used by Anthropic. Labels in brackets are Epoch AI's confidence where it is not "confident".
How reliable is the power around Colossus 1?
In Shelby County, the average customer is without power about 15 hours in a typical year in this site's outage record, with 5 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.
What power plants are near Colossus 1?
4 plants within 15 miles total about 2.47 GW; the largest is Allen (1.29 GW, natural gas), 4.3 miles away. Nearness does not mean it supplies the campus.
Epoch AI's sources for this campus
- May 2025 Electricity Provider Disclosure
- July 2025 Permit for Gas Turbines
- Southern Environmental Law Center Gas Permit Appeal, with additional satellite images
- Disclosure on X (formerly Twitter) by Elon Musk of the breakdown of GPUs
- Anthropic announcement
Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.