AI data center · Memphis, Tennessee
Colossus 2
SpaceXAI's AI campus in Shelby County. It draws about 946 MW today and is planned to reach 2.06 GW by February 2027.
Latest look · Jun 15, 2026
What the satellite shows
The site is estimated to have at least ~830 MW of GPU server power, with at least "at least 220,000 additional GB300 processors and over 400 additional megawatts of compute power", corresponding to the "next phase of expansion" found in the following company S-1 filing, page 76. This estimate is backed up by our cooling and turbine based power production calculations. The cooling calculations suggest there is enough infrastructure to support ~850MW of IT Power. Similarly the energy production calculations support ~900MW of available IT Power. This gives us confidence that the proposed expansion was achieved in time. The roof for building 3 is halfway complete.
Build-out
Power, month by month
Who
Owners, users and builders
- Owner
- SpaceXAI
- Used by
- Anthropic, Cursor, SpaceXAI
- Chips
- B200, B300
- Address
- 5420 Tulane Rd, Memphis, TN 38109
- County
- Shelby County
Where
On the map of Tennessee
Placed by its street address.
Nearby
Power plants within 15 miles
| Plant | Source | Capacity | Distance |
|---|---|---|---|
| Allen | ● Natural gas | 1.29 GW | 7.9 mi |
| TVA Southaven Combined Cycle | ● Natural gas | 904 MW | 0.5 mi |
| Wildflower Solar, LLC (MS) | ● Solar | 100 MW | 8.4 mi |
Timeline
Every observation
| Date | What Epoch AI saw | Power |
|---|---|---|
| Jun 15, 2026 | The site is estimated to have at least ~830 MW of GPU server power, with at least "at least 220,000 additional GB300 processors and over 400 additional megawatts of compute power", corresponding to the "next phase of expansion" found in the following company S-1 filing, page 76. This estimate is backed up by our cooling and turbine based power production calculations. The cooling calculations suggest there is enough infrastructure to support ~850MW of IT Power. Similarly the energy production calculations support ~900MW of available IT Power. This gives us confidence that the proposed expansion was achieved in time. The roof for building 3 is halfway complete. | 1.28 GW |
| Apr 6, 2026 | The first array of dry cooling air-cooled condensers for Building 1 has been completed and is operational. A second array, with larger fans, is about halfway complete (located to the south of the first array). More chillers have also been added. For Building 2, an array of dry cooling air-cooled condensers of the same type as Building 1's first array is beginning construction. We believe this corresponds to the "second cluster of 110,000 GB300 processors and 220 megawatts of compute power" from the company S-1 filing, page 76, with compute power corresponding to GPU server power. This is also consistent with our estimates based on cooling equipment. | 661 MW |
| Jan 13, 2026 | Since October, an array of dry cooling air-cooled condensers has been added (the array of large fans to the left of the building), and appears almost complete. Two more similar arrays appear to be under construction. More air-cooled chillers, batteries, and gas turbines have also been installed. | 323 MW |
| Oct 19, 2025 | Battery facility looks complete (though more might be added). Turbines look connected up, minimal construction around them. We believe this state corresponds to the first compute cluster brought online at this site of "approximately 110,000 GB200 processors, approximately 210 megawatts of compute power", as detailed in the company S-1 filing, page 76. Based on those numbers, we believe "compute power" corresponds to GPU server power. Earlier tweets from Elon Musk also support this timing, and it's consistent with the estimated cooling capacity based on the satellite image. | 323 MW |
| Sep 8, 2025 | Battery facility connected to the building. 121 air-cooled chillers installed, which could support 200 MW. In the Duke faciltiy in nearby Mississippi, several natural gas turbines are in place but not fully connected up. | – |
| Feb 28, 2025 | Land clearing begins next to the existing building. | – |
Plus 1 projected step to February 2027, from Epoch AI's reading of the build plans.
How much power does Colossus 2 use?
About 946 MW as of Jun 15, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 2.06 GW in its build plans by February 2027. Running all year, 946 MW would use about 8.3 TWh.
Who owns Colossus 2?
SpaceXAI; used by Anthropic, Cursor, SpaceXAI. Labels in brackets are Epoch AI's confidence where it is not "confident".
How reliable is the power around Colossus 2?
In Shelby County, the average customer is without power about 15 hours in a typical year in this site's outage record, with 5 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.
What power plants are near Colossus 2?
3 plants within 15 miles total about 2.29 GW; the largest is Allen (1.29 GW, natural gas), 7.9 miles away. Nearness does not mean it supplies the campus.
Epoch AI's sources for this campus
- WSJ profile of the Colossus data centers
- Final GPU count reported by Elon Musk
- MLGW update mentioning power requests for Colossus 2
- SpaceX-Cursor partnership to use Colossus
- Anthropic to use Colossus 2 from June 2026
- SpaceX S-1 filing, mentioning exact compute and power for Colossus 2
Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.