AI data center · Memphis, Tennessee

Colossus 2

SpaceXAI's AI campus in Shelby County. It draws about 946 MW today and is planned to reach 2.06 GW by February 2027.

Power now946 MWAs of Jun 15, 2026
Planned peak2.06 GWFebruary 2027
Compute1.11MH100-equivalent chips now
Capital cost$36BSo far, 2025 dollars

Latest look · Jun 15, 2026

What the satellite shows

The site is estimated to have at least ~830 MW of GPU server power, with at least "at least 220,000 additional GB300 processors and over 400 additional megawatts of compute power", corresponding to the "next phase of expansion" found in the following company S-1 filing, page 76. This estimate is backed up by our cooling and turbine based power production calculations. The cooling calculations suggest there is enough infrastructure to support ~850MW of IT Power. Similarly the energy production calculations support ~900MW of available IT Power. This gives us confidence that the proposed expansion was achieved in time. The roof for building 3 is halfway complete.

Build-out

Power, month by month

0 MW500 MW1 GW1.5 GW2 GW2.5 GW20262027Today
Power drawn by Colossus 2, from Epoch AI's dated observations and (hatched) its projections.
0 MW500 MW1 GW1.5 GW2 GW2.5 GW20262027Today
Power drawn by Colossus 2, from Epoch AI's dated observations and (hatched) its projections.

Who

Owners, users and builders

Owner
SpaceXAI
Used by
Anthropic, Cursor, SpaceXAI
Chips
B200, B300
Address
5420 Tulane Rd, Memphis, TN 38109
County
Shelby County

Where

On the map of Tennessee

Operating or permitted data center AI campus, power drawn now Planned peak (Epoch AI)

Placed by its street address.

Nearby

Power plants within 15 miles

PlantSourceCapacityDistance
Allen● Natural gas1.29 GW7.9 mi
TVA Southaven Combined Cycle● Natural gas904 MW0.5 mi
Wildflower Solar, LLC (MS)● Solar100 MW8.4 mi

Timeline

Every observation

DateWhat Epoch AI sawPower
Jun 15, 2026The site is estimated to have at least ~830 MW of GPU server power, with at least "at least 220,000 additional GB300 processors and over 400 additional megawatts of compute power", corresponding to the "next phase of expansion" found in the following company S-1 filing, page 76. This estimate is backed up by our cooling and turbine based power production calculations. The cooling calculations suggest there is enough infrastructure to support ~850MW of IT Power. Similarly the energy production calculations support ~900MW of available IT Power. This gives us confidence that the proposed expansion was achieved in time. The roof for building 3 is halfway complete.1.28 GW
Apr 6, 2026The first array of dry cooling air-cooled condensers for Building 1 has been completed and is operational. A second array, with larger fans, is about halfway complete (located to the south of the first array). More chillers have also been added. For Building 2, an array of dry cooling air-cooled condensers of the same type as Building 1's first array is beginning construction. We believe this corresponds to the "second cluster of 110,000 GB300 processors and 220 megawatts of compute power" from the company S-1 filing, page 76, with compute power corresponding to GPU server power. This is also consistent with our estimates based on cooling equipment.661 MW
Jan 13, 2026Since October, an array of dry cooling air-cooled condensers has been added (the array of large fans to the left of the building), and appears almost complete. Two more similar arrays appear to be under construction. More air-cooled chillers, batteries, and gas turbines have also been installed.323 MW
Oct 19, 2025Battery facility looks complete (though more might be added). Turbines look connected up, minimal construction around them. We believe this state corresponds to the first compute cluster brought online at this site of "approximately 110,000 GB200 processors, approximately 210 megawatts of compute power", as detailed in the company S-1 filing, page 76. Based on those numbers, we believe "compute power" corresponds to GPU server power. Earlier tweets from Elon Musk also support this timing, and it's consistent with the estimated cooling capacity based on the satellite image.323 MW
Sep 8, 2025Battery facility connected to the building. 121 air-cooled chillers installed, which could support 200 MW. In the Duke faciltiy in nearby Mississippi, several natural gas turbines are in place but not fully connected up.–
Feb 28, 2025Land clearing begins next to the existing building.–

Plus 1 projected step to February 2027, from Epoch AI's reading of the build plans.

How much power does Colossus 2 use?

About 946 MW as of Jun 15, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 2.06 GW in its build plans by February 2027. Running all year, 946 MW would use about 8.3 TWh.

Who owns Colossus 2?

SpaceXAI; used by Anthropic, Cursor, SpaceXAI. Labels in brackets are Epoch AI's confidence where it is not "confident".

How reliable is the power around Colossus 2?

In Shelby County, the average customer is without power about 15 hours in a typical year in this site's outage record, with 5 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.

What power plants are near Colossus 2?

3 plants within 15 miles total about 2.29 GW; the largest is Allen (1.29 GW, natural gas), 7.9 miles away. Nearness does not mean it supplies the campus.

Epoch AI's sources for this campus

Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.