AI data center · Kuna, Idaho
Meta Kuna
Meta's AI campus in Ada County. It draws about 152 MW today and is planned to reach 198 MW by June 2026.
Latest look · Jun 1, 2026
What the satellite shows
Building 1 and 2 are operational. The 2nd phase of an offsetting solar array goes online on May 31, 2026. Idaho Public Utilities Comission's approval for this start date notes that "[Meta]’s load is expected to increase so much that it will suffer a capacity deficit in June 2026 if served only by Pleasant Valley Solar 1.1,” A redacted table in the staff comments document suggests the data center's load will continue to increase through August, when it presumably reaches the maximum capacity of both buildings.
Build-out
Power, month by month
Who
Owners, users and builders
- Owner
- Meta
- Used by
- Meta
- Energy companies
- Idaho Power Company
- Chips
- B300
- Water use
- 0.07 million gallons a day (Epoch AI estimate)
- Address
- 601 Kuna Mora Rd, Kuna ID 83634
- County
- Ada County
Where
On the map of Idaho
Placed by its street address.
Nearby
Power plants within 15 miles
| Plant | Source | Capacity | Distance |
|---|---|---|---|
| Hemmingway BESS | ● Storage | 166 MW | 14.2 mi |
| Kuna BESS | ● Storage | 150 MW | 2.1 mi |
| Boise Bench BESS | ● Storage | 150 MW | 15 mi |
| Happy Valley Battery Storage | ● Storage | 82 MW | 7.8 mi |
| ID Solar | ● Solar | 40 MW | 4.5 mi |
| Orchard Ranch Solar | ● Solar | 20 MW | 6.6 mi |
| Amalgamated Sugar LLC Nampa | ● Natural gas | 8 MW | 12.7 mi |
| MC6 Hydro Facility | ● Hydro | 2 MW | 3.8 mi |
Timeline
Every observation
| Date | What Epoch AI saw | Power |
|---|---|---|
| Jun 1, 2026 | Building 1 and 2 are operational. The 2nd phase of an offsetting solar array goes online on May 31, 2026. Idaho Public Utilities Comission's approval for this start date notes that "[Meta]’s load is expected to increase so much that it will suffer a capacity deficit in June 2026 if served only by Pleasant Valley Solar 1.1,” A redacted table in the staff comments document suggests the data center's load will continue to increase through August, when it presumably reaches the maximum capacity of both buildings. | 198 MW |
| Mar 15, 2026 | Building 1 and 2 look complete from outside, with all electrical and cooling equipment installed. Construction has started on 2 smaller buildings to the north. Meta announced the arrival of the first server rack the following week. | – |
| Jul 1, 2022 | Land clearing begins. | – |
How much power does Meta Kuna use?
About 152 MW as of Jun 1, 2026, by Epoch AI's estimate of the whole facility's draw, rising to about 198 MW in its build plans by June 2026. Running all year, 152 MW would use about 1.3 TWh.
Who owns Meta Kuna?
Meta; used by Meta. Labels in brackets are Epoch AI's confidence where it is not "confident".
How reliable is the power around Meta Kuna?
In Ada County, the average customer is without power about 1.1 hours in a typical year in this site's outage record, with 0 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.
What power plants are near Meta Kuna?
8 plants within 15 miles total about 622 MW; the largest is Hemmingway BESS (166 MW, storage), 14.2 miles away. Nearness does not mean it supplies the campus.
Epoch AI's sources for this campus
- Official Pamphlet from Meta
- Application for Power Purchase Agreement, Pleasant Valley Solar 1
- Application for Power Purchase Agreement, Pleasant Valley Solar 2
- Approval to move start date of Solar 2 to May 31, 2026
- staff comments
- Notice of Application for 3rd PPA (Blacks Creek Energy Center)
- Idaho Statesman: Peak construction reached in March 2025
- Idaho Statesman: Expected water usage reported in 2022
Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.