AI data center · Benton, Michigan
OpenAI Stargate Michigan
Oracle's AI campus in Washtenaw County. It is not drawing power yet and is planned to reach 1.38 GW by December 2028.
Latest look · Mar 12, 2026
What the satellite shows
Groundwork is visible for Building 1, at the left end of the site.
Build-out
Power, month by month
Who
Owners, users and builders
- Owner
- Oracle
- Used by
- OpenAI
- Project
- Stargate
- County
- Washtenaw County
Where
On the map of Michigan
Placed at the industrial area or township Epoch's sources name; the exact site is not mapped here.
Nearby
Power plants within 15 miles
| Plant | Source | Capacity | Distance |
|---|---|---|---|
| White Tail Solar | ● Solar | 140 MW | 9.5 mi |
| Superior | ● Oil | 64 MW | 13.9 mi |
| University of Michigan | ● Natural gas | 60 MW | 12.1 mi |
| Warner Lambert | ● Oil | 12 MW | 13.9 mi |
| East. Michigan Univ. Heating Plant | ● Natural gas | 8 MW | 13.8 mi |
| Hendershot Solar, LLC | ● Solar | 2 MW | 10.1 mi |
Timeline
Every observation
| Date | What Epoch AI saw | Power |
|---|---|---|
| Mar 12, 2026 | Groundwork is visible for Building 1, at the left end of the site. | – |
| Jan 20, 2026 | Land clearing continues for all buildings (1-3) | – |
| Dec 4, 2025 | Land clearing begins for the entire site | – |
Plus 1 projected step to December 2028, from Epoch AI's reading of the build plans.
How much power does OpenAI Stargate Michigan use?
It is not drawing power yet in Epoch AI's timeline; it is planned to reach about 1.38 GW by December 2028.
Who owns OpenAI Stargate Michigan?
Oracle; used by OpenAI. Labels in brackets are Epoch AI's confidence where it is not "confident".
How reliable is the power around OpenAI Stargate Michigan?
In Washtenaw County, the average customer is without power about 16 hours in a typical year in this site's outage record, with 7 major outage events since 2014. A campus this size takes power from the high-voltage grid and has its own backup, so household figures describe the area, not the campus.
What power plants are near OpenAI Stargate Michigan?
6 plants within 15 miles total about 286 MW; the largest is White Tail Solar (140 MW, solar), 9.5 miles away. Nearness does not mean it supplies the campus.
Epoch AI's sources for this campus
- Related Digital website for this site
- Michigan Public Service Commission Energy Contract Approval, reports 1,383 MW as the site capacity
- Air Permitting, calls the site Project Mitten, includes site map
- DTE Electric’s contract approval
- Website with more details for locals about the site
Source: Epoch AI, "AI data centers", CC BY 4.0, read Nov 17, 2026. Power, compute and cost are Epoch's estimates; timeline rows after today are its projections. Power plants: EIA-860M. Outage record: ORNL EAGLE-I.