Storage power plant · Sussex, NJ
Andover Energy Storage Project
Andover Energy Storage Project is a 20 MW storage power plant in Sussex County, New Jersey, operated by VESI 25 LLC. Its oldest generator still running came online in 2023.
Andover Energy Storage Project in context
Among the 13 storage plants in New Jersey in the EIA's inventory, it is the 2nd largest, about 3.4% of the state's 585 MW of storage capacity.
Sussex County has 9 power plants of 1 MW or more with 74 MW in all; Andover Energy Storage Project is 27% of that and the largest of 2 storage plants there.
The average electricity customer in Sussex County goes 31 hours a year without power, the 1st most of 21 counties in New Jersey. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923. Storage uses more energy charging than it returns, so its net figure is negative.
Where it is
Andover Energy Storage Project (outlined) and other plants in Sussex County, shaded. 40.981, -74.761.
Plant facts
- Operator
- VESI 25 LLC
- Sector
- IPP Non-CHP
- Grid operator
- PJM
- County
- Sussex County, NJ
- EIA plant ID
- 65952
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| AD1 | Batteries | 20 MW · 20 MWh | 2023 | – |
Nearby
Other plants in Sussex County
Questions
Andover Energy Storage Project, answered
How much can Andover Energy Storage Project store and deliver?
Andover Energy Storage Project can deliver up to 20 MW and hold 20 MWh of energy, from one battery or storage system. Its net energy in 2025 was -4.0 GWh: a storage plant uses more energy charging than it returns, so the figure is usually negative.
Where is Andover Energy Storage Project?
Andover Energy Storage Project is in Sussex County, New Jersey, at about 40.981°, -74.761°. It is one of 9 power plants of 1 MW or more in the county. The average electricity customer in Sussex County goes 31 hours a year without power, the 1st most of 21 counties in New Jersey. The county's page has the full outage record.
Who operates Andover Energy Storage Project?
It is operated by VESI 25 LLC (EIA sector: IPP Non-CHP), and it feeds PJM Interconnection.
When did Andover Energy Storage Project open?
Its oldest generator still running came online in 2023.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2024–2025). Methodology.