Wind power plant · Coke, TX

Aviator Wind

Aviator Wind is a 525 MW wind power plant in Coke County, Texas, operated by Aviator Wind, LLC. Its oldest generator still running came online in 2021. In 2025 it generated 1.7 TWh, about what 127,000 average Texas homes use in a year.

Capacity525 MWNameplate, September 2026
Generated1.7 TWhIn 2025
Capacity factor37%Share of the most it could make, 2025
Generators1Oldest from 2021

Aviator Wind in context

Among the 230 wind plants in Texas in the EIA's inventory, it is the 5th largest, about 1.2% of the state's 45 GW of wind capacity.

Coke County has 2 power plants of 1 MW or more with 527 MW in all; Aviator Wind is 100% of that.

Its capacity factor of 37% in 2025 is close to the 32% typical for wind plants across the US.

The average electricity customer in Coke County goes 24 hours a year without power, the 28th most of 240 counties in Texas. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

05001,0001,5002,0002,50020212022202320242025GWh 1,698
05001,0001,5002,0002,500202120222023202420251,698

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Aviator Wind (outlined) and other plants in Coke County, shaded. 31.793, -100.697.

Plant facts

Operator
Aviator Wind, LLC
Sector
IPP Non-CHP
Grid operator
ERCO
County
Coke County, TX
EIA plant ID
63209
Where Texas's power comes from → Texas power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
AVTOR Onshore Wind Turbine 525 MW 2021 –

Nearby

Other plants in Coke County

Jameson Gas Processing Plant · 1.8 MW

Questions

Aviator Wind, answered

How much power does Aviator Wind produce?

Aviator Wind has 525 MW of capacity from one generator. In 2025 it generated 1.7 TWh, 37% of the most it could have made running flat out all year (its capacity factor).

How many homes does Aviator Wind power?

Its 2025 output of 1.7 TWh equals the yearly electricity use of about 127,000 average Texas homes (1,110 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Aviator Wind?

Aviator Wind is in Coke County, Texas, at about 31.793°, -100.697°. It is one of 2 power plants of 1 MW or more in the county. The average electricity customer in Coke County goes 24 hours a year without power, the 28th most of 240 counties in Texas. The county's page has the full outage record.

Who operates Aviator Wind?

It is operated by Aviator Wind, LLC (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.

When did Aviator Wind open?

Its oldest generator still running came online in 2021.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2021–2025). Homes equivalent uses the average Texas home's 1,110 kWh a month in 2025. Methodology.