Wind power plant · Coke, TX
Aviator Wind
Aviator Wind is a 525 MW wind power plant in Coke County, Texas, operated by Aviator Wind, LLC. Its oldest generator still running came online in 2021. In 2025 it generated 1.7 TWh, about what 127,000 average Texas homes use in a year.
Aviator Wind in context
Among the 230 wind plants in Texas in the EIA's inventory, it is the 5th largest, about 1.2% of the state's 45 GW of wind capacity.
Coke County has 2 power plants of 1 MW or more with 527 MW in all; Aviator Wind is 100% of that.
Its capacity factor of 37% in 2025 is close to the 32% typical for wind plants across the US.
The average electricity customer in Coke County goes 24 hours a year without power, the 28th most of 240 counties in Texas. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Aviator Wind (outlined) and other plants in Coke County, shaded. 31.793, -100.697.
Plant facts
- Operator
- Aviator Wind, LLC
- Sector
- IPP Non-CHP
- Grid operator
- ERCO
- County
- Coke County, TX
- EIA plant ID
- 63209
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| AVTOR | Onshore Wind Turbine | 525 MW | 2021 | – |
Nearby
Other plants in Coke County
Questions
Aviator Wind, answered
How much power does Aviator Wind produce?
Aviator Wind has 525 MW of capacity from one generator. In 2025 it generated 1.7 TWh, 37% of the most it could have made running flat out all year (its capacity factor).
How many homes does Aviator Wind power?
Its 2025 output of 1.7 TWh equals the yearly electricity use of about 127,000 average Texas homes (1,110 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Aviator Wind?
Aviator Wind is in Coke County, Texas, at about 31.793°, -100.697°. It is one of 2 power plants of 1 MW or more in the county. The average electricity customer in Coke County goes 24 hours a year without power, the 28th most of 240 counties in Texas. The county's page has the full outage record.
Who operates Aviator Wind?
It is operated by Aviator Wind, LLC (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.
When did Aviator Wind open?
Its oldest generator still running came online in 2021.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2021–2025). Homes equivalent uses the average Texas home's 1,110 kWh a month in 2025. Methodology.