Wind power plant · Faribault, MN
Big Blue
Big Blue is a 36 MW wind power plant in Faribault County, Minnesota, operated by Big Blue Wind Farm LLC (MN). Its oldest generator still running came online in 2012. In 2025 it generated 71 GWh, about what 7,900 average Minnesota homes use in a year.
Big Blue in context
Among the 122 wind plants in Minnesota in the EIA's inventory, it is the 35th largest, about 0.7% of the state's 5.0 GW of wind capacity.
Faribault County has 6 power plants of 1 MW or more with 60 MW in all; Big Blue is 60% of that and the largest of 3 wind plants there.
Its capacity factor of 22% in 2025 is lower than the 32% typical for wind plants across the US.
The average electricity customer in Faribault County goes 1.1 hours a year without power. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Big Blue (outlined) and other plants in Faribault County, shaded. 43.612, -94.192.
Plant facts
- Operator
- Big Blue Wind Farm LLC (MN)
- Sector
- IPP Non-CHP
- Grid operator
- MISO
- County
- Faribault County, MN
- EIA plant ID
- 57289
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| BBWP | Onshore Wind Turbine | 36 MW | 2012 | – |
Nearby
Other plants in Faribault County
Questions
Big Blue, answered
How much power does Big Blue produce?
Big Blue has 36 MW of capacity from one generator. In 2025 it generated 71 GWh, 22% of the most it could have made running flat out all year (its capacity factor).
How many homes does Big Blue power?
Its 2025 output of 71 GWh equals the yearly electricity use of about 7,900 average Minnesota homes (743 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Big Blue?
Big Blue is in Faribault County, Minnesota, at about 43.612°, -94.192°. It is one of 6 power plants of 1 MW or more in the county. The average electricity customer in Faribault County goes 1.1 hours a year without power. The county's page has the full outage record.
Who operates Big Blue?
It is operated by Big Blue Wind Farm LLC (MN) (EIA sector: IPP Non-CHP), and it feeds MISO.
When did Big Blue open?
Its oldest generator still running came online in 2012.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Minnesota home's 743 kWh a month in 2025. Methodology.