Biomass power plant · Dickinson, MI
Billerud Quinnesec Mill
Billerud Quinnesec Mill is a 56 MW biomass power plant in Dickinson County, Michigan, operated by Billerud Quinnesec Mill. Its oldest generator still running came online in 1985. In 2025 it generated 318 GWh, about what 42,000 average Michigan homes use in a year.
Billerud Quinnesec Mill in context
Among the 57 other-fuel plants in Michigan in the EIA's inventory, it is the 3rd largest, about 6.4% of the state's 873 MW of other-fuel capacity.
Dickinson County has 5 power plants of 1 MW or more with 90 MW in all; Billerud Quinnesec Mill is 62% of that.
Its capacity factor of 65% in 2025 is higher than the 25% typical for biomass plants across the US.
The average electricity customer in Dickinson County goes 8.7 hours a year without power, the 62nd most of 83 counties in Michigan. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Billerud Quinnesec Mill (outlined) and other plants in Dickinson County, shaded. 45.796, -87.956.
Plant facts
- Operator
- Billerud Quinnesec Mill
- Sector
- Industrial CHP
- Grid operator
- MISO
- County
- Dickinson County, MI
- EIA plant ID
- 50251
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| GEN1 | Wood/Wood Waste Biomass | 28 MW | 1985 | – |
| GEN2 | Wood/Wood Waste Biomass | 28 MW | 2011 | – |
Nearby
Other plants in Dickinson County
Questions
Billerud Quinnesec Mill, answered
How much power does Billerud Quinnesec Mill produce?
Billerud Quinnesec Mill has 56 MW of capacity from 2 generators. In 2025 it generated 318 GWh, 65% of the most it could have made running flat out all year (its capacity factor).
How many homes does Billerud Quinnesec Mill power?
Its 2025 output of 318 GWh equals the yearly electricity use of about 42,000 average Michigan homes (635 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Billerud Quinnesec Mill?
Billerud Quinnesec Mill is in Dickinson County, Michigan, at about 45.796°, -87.956°. It is one of 5 power plants of 1 MW or more in the county. The average electricity customer in Dickinson County goes 8.7 hours a year without power, the 62nd most of 83 counties in Michigan. The county's page has the full outage record.
Who operates Billerud Quinnesec Mill?
It is operated by Billerud Quinnesec Mill (EIA sector: Industrial CHP), and it feeds MISO.
When did Billerud Quinnesec Mill open?
Its oldest generator still running came online in 1985.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Michigan home's 635 kWh a month in 2025. Methodology.