Other power plant · Hutchinson, TX
Borger Plant
Borger Plant is a 30 MW other power plant in Hutchinson County, Texas, operated by Sid Richardson Carbon Ltd. Its oldest generator still running came online in 1985.
Borger Plant in context
Among the 50 other-fuel plants in Texas in the EIA's inventory, it is the 12th largest, about 1.8% of the state's 1.6 GW of other-fuel capacity.
Hutchinson County has 3 power plants of 1 MW or more with 294 MW in all; Borger Plant is 10% of that and the largest of 2 other plants there.
The average electricity customer in Hutchinson County goes 15 hours a year without power, the 75th most of 240 counties in Texas. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Where it is
Borger Plant (outlined) and other plants in Hutchinson County, shaded. 35.665, -101.435.
Plant facts
- Operator
- Sid Richardson Carbon Ltd
- Sector
- Industrial CHP
- Grid operator
- SWPP
- County
- Hutchinson County, TX
- EIA plant ID
- 50067
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| GEN1 | Other Gases | 30 MW | 1985 | – |
Nearby
Other plants in Hutchinson County
Questions
Borger Plant, answered
How much power does Borger Plant produce?
Borger Plant has 30 MW of capacity from one generator. No full year of generation is reported yet.
Where is Borger Plant?
Borger Plant is in Hutchinson County, Texas, at about 35.665°, -101.435°. It is one of 3 power plants of 1 MW or more in the county. The average electricity customer in Hutchinson County goes 15 hours a year without power, the 75th most of 240 counties in Texas. The county's page has the full outage record.
Who operates Borger Plant?
It is operated by Sid Richardson Carbon Ltd (EIA sector: Industrial CHP), and it feeds the Southwest Power Pool.
When did Borger Plant open?
Its oldest generator still running came online in 1985.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Methodology.