Solar power plant · Bosque, TX
BT Hickerson Solar, LLC
BT Hickerson Solar, LLC is a 310 MW solar power plant in Bosque County, Texas, operated by BT Hickerson Solar, LLC. Its oldest generator still running came online in 2025. In 2025 it generated 206 GWh, about what 15,000 average Texas homes use in a year.
BT Hickerson Solar, LLC in context
Among the 250 solar plants in Texas in the EIA's inventory, it is the 28th largest, about 0.8% of the state's 37 GW of solar capacity.
Bosque County has 7 power plants of 1 MW or more with 1.3 GW in all; BT Hickerson Solar, LLC is 23% of that and the largest of 5 solar plants there.
The average electricity customer in Bosque County goes 11 hours a year without power, the 112th most of 240 counties in Texas. The county's page has the full outage record.
Seasons
Month by month, 2025
Where it is
BT Hickerson Solar, LLC (outlined) and other plants in Bosque County, shaded. 31.820, -97.517.
Plant facts
- Operator
- BT Hickerson Solar, LLC
- Sector
- IPP Non-CHP
- Grid operator
- ERCO
- County
- Bosque County, TX
- EIA plant ID
- 66903
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 5105 | Solar Photovoltaic | 310 MW | 2025 | – |
Nearby
Other plants in Bosque County
Questions
BT Hickerson Solar, LLC, answered
How much power does BT Hickerson Solar, LLC produce?
BT Hickerson Solar, LLC has 310 MW of capacity from one generator. In 2025 it generated 206 GWh.
How many homes does BT Hickerson Solar, LLC power?
Its 2025 output of 206 GWh equals the yearly electricity use of about 15,000 average Texas homes (1,110 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is BT Hickerson Solar, LLC?
BT Hickerson Solar, LLC is in Bosque County, Texas, at about 31.820°, -97.517°. It is one of 7 power plants of 1 MW or more in the county. The average electricity customer in Bosque County goes 11 hours a year without power, the 112th most of 240 counties in Texas. The county's page has the full outage record.
Who operates BT Hickerson Solar, LLC?
It is operated by BT Hickerson Solar, LLC (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.
When did BT Hickerson Solar, LLC open?
Its oldest generator still running came online in 2025.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2025–2025). Homes equivalent uses the average Texas home's 1,110 kWh a month in 2025. Methodology.