Wind power plant · Ellis, KS

Buckeye Wind Energy Center

Buckeye Wind Energy Center is a 201 MW wind power plant in Ellis County, Kansas, operated by Invenergy Services LLC. Its oldest generator still running came online in 2015. In 2025 it generated 561 GWh, about what 53,000 average Kansas homes use in a year.

Capacity201 MWNameplate, September 2026
Generated561 GWhIn 2025
Capacity factor32%Share of the most it could make, 2025
Generators1Oldest from 2015

Buckeye Wind Energy Center in context

Among the 52 wind plants in Kansas in the EIA's inventory, it is the 19th largest, about 2.1% of the state's 9.7 GW of wind capacity.

Ellis County has 3 power plants of 1 MW or more with 308 MW in all; Buckeye Wind Energy Center is 65% of that and the largest of 2 wind plants there.

Its capacity factor of 32% in 2025 is close to the 32% typical for wind plants across the US.

The average electricity customer in Ellis County goes 3.7 hours a year without power, the 36th most of 81 counties in Kansas. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

02004006008001,00020182019202020212022202320242025GWh 561
02004006008001,0002019202120232025561

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Buckeye Wind Energy Center (outlined) and other plants in Ellis County, shaded. 39.004, -99.414.

Plant facts

Operator
Invenergy Services LLC
Sector
IPP Non-CHP
Grid operator
SWPP
County
Ellis County, KS
EIA plant ID
58767
Where Kansas's power comes from → Kansas power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
1 Onshore Wind Turbine 201 MW 2015 –

Nearby

Other plants in Ellis County

Goodman Energy Center · 104 MWFort Hays State University Wind Farm · 4.0 MW

Questions

Buckeye Wind Energy Center, answered

How much power does Buckeye Wind Energy Center produce?

Buckeye Wind Energy Center has 201 MW of capacity from one generator. In 2025 it generated 561 GWh, 32% of the most it could have made running flat out all year (its capacity factor).

How many homes does Buckeye Wind Energy Center power?

Its 2025 output of 561 GWh equals the yearly electricity use of about 53,000 average Kansas homes (876 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Buckeye Wind Energy Center?

Buckeye Wind Energy Center is in Ellis County, Kansas, at about 39.004°, -99.414°. It is one of 3 power plants of 1 MW or more in the county. The average electricity customer in Ellis County goes 3.7 hours a year without power, the 36th most of 81 counties in Kansas. The county's page has the full outage record.

Who operates Buckeye Wind Energy Center?

It is operated by Invenergy Services LLC (EIA sector: IPP Non-CHP), and it feeds the Southwest Power Pool.

When did Buckeye Wind Energy Center open?

Its oldest generator still running came online in 2015.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Kansas home's 876 kWh a month in 2025. Methodology.