Natural gas power plant · Suffolk, NY
Caithness Long Island Energy Center
Caithness Long Island Energy Center is a 349 MW natural gas power plant in Suffolk County, New York, operated by Caithness Long Island, LLC. Its oldest generator still running came online in 2009. In 2025 it generated 2.4 TWh, about what 340,000 average New York homes use in a year.
Caithness Long Island Energy Center in context
Among the 103 natural gas plants in New York in the EIA's inventory, it is the 22nd largest, about 1.5% of the state's 24 GW of natural gas capacity.
Suffolk County has 57 power plants of 1 MW or more with 4.4 GW in all; Caithness Long Island Energy Center is 8% of that and the 3rd largest of 13 natural gas plants there.
Its capacity factor of 78% in 2025 is higher than the 23% typical for natural gas plants across the US.
The average electricity customer in Suffolk County goes 4.5 hours a year without power, the 43rd most of 62 counties in New York. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Caithness Long Island Energy Center (outlined) and other plants in Suffolk County, shaded. 40.814, -72.940.
Plant facts
- Operator
- Caithness Long Island, LLC
- Sector
- IPP Non-CHP
- Grid operator
- NYIS
- County
- Suffolk County, NY
- EIA plant ID
- 56234
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| CT01 | Natural Gas Fired Combined Cycle | 196 MW | 2009 | – |
| ST01 | Natural Gas Fired Combined Cycle | 153 MW | 2009 | – |
Questions
Caithness Long Island Energy Center, answered
How much power does Caithness Long Island Energy Center produce?
Caithness Long Island Energy Center has 349 MW of capacity from 2 generators. In 2025 it generated 2.4 TWh, 78% of the most it could have made running flat out all year (its capacity factor).
How many homes does Caithness Long Island Energy Center power?
Its 2025 output of 2.4 TWh equals the yearly electricity use of about 340,000 average New York homes (586 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Caithness Long Island Energy Center?
Caithness Long Island Energy Center is in Suffolk County, New York, at about 40.814°, -72.940°. It is one of 57 power plants of 1 MW or more in the county. The average electricity customer in Suffolk County goes 4.5 hours a year without power, the 43rd most of 62 counties in New York. The county's page has the full outage record.
Who operates Caithness Long Island Energy Center?
It is operated by Caithness Long Island, LLC (EIA sector: IPP Non-CHP), and it feeds the New York ISO.
When did Caithness Long Island Energy Center open?
Its oldest generator still running came online in 2009.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average New York home's 586 kWh a month in 2025. Methodology.