Solar power plant · Morrison, MN
Camp Ripley Solar
Camp Ripley Solar is a 11 MW solar power plant in Morrison County, Minnesota, operated by Camp Riley Solar Facility. Its oldest generator still running came online in 2016. In 2025 it generated 14 GWh, about what 1,600 average Minnesota homes use in a year.
Camp Ripley Solar in context
Among the 544 solar plants in Minnesota in the EIA's inventory, it is the 11th largest, about 0.5% of the state's 2.1 GW of solar capacity.
Morrison County has 3 power plants of 1 MW or more with 34 MW in all; Camp Ripley Solar is 33% of that.
Its capacity factor of 15% in 2025 is lower than the 20% typical for solar plants across the US.
The average electricity customer in Morrison County goes 3.8 hours a year without power, the 18th most of 54 counties in Minnesota. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Camp Ripley Solar (outlined) and other plants in Morrison County, shaded. 46.091, -94.340.
Plant facts
- Operator
- Camp Riley Solar Facility
- Sector
- Electric Utility
- Grid operator
- MISO
- County
- Morrison County, MN
- EIA plant ID
- 64072
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| CR1 | Solar Photovoltaic | 11 MW | 2016 | – |
Nearby
Other plants in Morrison County
Questions
Camp Ripley Solar, answered
How much power does Camp Ripley Solar produce?
Camp Ripley Solar has 11 MW of capacity from one generator. In 2025 it generated 14 GWh, 15% of the most it could have made running flat out all year (its capacity factor).
How many homes does Camp Ripley Solar power?
Its 2025 output of 14 GWh equals the yearly electricity use of about 1,600 average Minnesota homes (743 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Camp Ripley Solar?
Camp Ripley Solar is in Morrison County, Minnesota, at about 46.091°, -94.340°. It is one of 3 power plants of 1 MW or more in the county. The average electricity customer in Morrison County goes 3.8 hours a year without power, the 18th most of 54 counties in Minnesota. The county's page has the full outage record.
Who operates Camp Ripley Solar?
It is operated by Camp Riley Solar Facility (EIA sector: Electric Utility), and it feeds MISO.
When did Camp Ripley Solar open?
Its oldest generator still running came online in 2016.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2020–2025). Homes equivalent uses the average Minnesota home's 743 kWh a month in 2025. Methodology.