Solar power plant · Wharton, TX
Cascade Solar (TX)
Cascade Solar (TX) is a 10 MW solar power plant in Wharton County, Texas, operated by Headwater Energy, LLC. Its oldest generator still running came online in 2019. In 2025 it generated 5.8 GWh, about what 435 average Texas homes use in a year.
Cascade Solar (TX) in context
Among the 250 solar plants in Texas in the EIA's inventory, it is the 192nd largest, about 0.0% of the state's 37 GW of solar capacity.
Wharton County has 12 power plants of 1 MW or more with 3.9 GW in all; Cascade Solar (TX) is 0% of that and the 4th largest of 4 solar plants there.
Its capacity factor of 7% in 2025 is lower than the 20% typical for solar plants across the US.
The average electricity customer in Wharton County goes 36 hours a year without power, the 12th most of 240 counties in Texas. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Cascade Solar (TX) (outlined) and other plants in Wharton County, shaded. 29.205, -96.023.
Plant facts
- Operator
- Headwater Energy, LLC
- Sector
- IPP Non-CHP
- Grid operator
- ERCO
- County
- Wharton County, TX
- EIA plant ID
- 61875
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| GEN1 | Solar Photovoltaic | 10 MW | 2019 | – |
Questions
Cascade Solar (TX), answered
How much power does Cascade Solar (TX) produce?
Cascade Solar (TX) has 10 MW of capacity from one generator. In 2025 it generated 5.8 GWh, 7% of the most it could have made running flat out all year (its capacity factor).
How many homes does Cascade Solar (TX) power?
Its 2025 output of 5.8 GWh equals the yearly electricity use of about 435 average Texas homes (1,110 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Cascade Solar (TX)?
Cascade Solar (TX) is in Wharton County, Texas, at about 29.205°, -96.023°. It is one of 12 power plants of 1 MW or more in the county. The average electricity customer in Wharton County goes 36 hours a year without power, the 12th most of 240 counties in Texas. The county's page has the full outage record.
Who operates Cascade Solar (TX)?
It is operated by Headwater Energy, LLC (EIA sector: IPP Non-CHP), and it feeds ERCOT, the Texas grid.
When did Cascade Solar (TX) open?
Its oldest generator still running came online in 2019.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2019–2025). Homes equivalent uses the average Texas home's 1,110 kWh a month in 2025. Methodology.