Solar power plant · Jefferson, IL
Casey Fork Solar, LLC
Casey Fork Solar, LLC is a 150 MW solar power plant in Jefferson County, Illinois, operated by RWE Americas, LLC. Its oldest generator still running came online in 2026.
Casey Fork Solar, LLC in context
Among the 476 solar plants in Illinois in the EIA's inventory, it is the 13th largest, about 2.6% of the state's 5.9 GW of solar capacity.
Jefferson County has 2 power plants of 1 MW or more with 152 MW in all; Casey Fork Solar, LLC is 99% of that and the largest of 2 solar plants there.
The average electricity customer in Jefferson County goes 5.6 hours a year without power, the 34th most of 101 counties in Illinois. The county's page has the full outage record.
Where it is
Casey Fork Solar, LLC (outlined) and other plants in Jefferson County, shaded. 38.452, -88.876.
Plant facts
- Operator
- RWE Americas, LLC
- Sector
- IPP Non-CHP
- Grid operator
- MISO
- County
- Jefferson County, IL
- EIA plant ID
- 69578
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| CFSPV | Solar Photovoltaic | 150 MW | 2026 | – |
Nearby
Other plants in Jefferson County
Questions
Casey Fork Solar, LLC, answered
How much power does Casey Fork Solar, LLC produce?
Casey Fork Solar, LLC has 150 MW of capacity from one generator. No full year of generation is reported yet.
Where is Casey Fork Solar, LLC?
Casey Fork Solar, LLC is in Jefferson County, Illinois, at about 38.452°, -88.876°. It is one of 2 power plants of 1 MW or more in the county. The average electricity customer in Jefferson County goes 5.6 hours a year without power, the 34th most of 101 counties in Illinois. The county's page has the full outage record.
Who operates Casey Fork Solar, LLC?
It is operated by RWE Americas, LLC (EIA sector: IPP Non-CHP), and it feeds MISO.
When did Casey Fork Solar, LLC open?
Its oldest generator still running came online in 2026.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2025–2025). Methodology.