Solar power plant · Lenawee, MI

Cement City Solar, LLC

Cement City Solar, LLC is a 20 MW solar power plant in Lenawee County, Michigan, operated by AES Distributed Energy. Its oldest generator still running came online in 2023. In 2025 it generated 32 GWh, about what 4,200 average Michigan homes use in a year.

Capacity20 MWNameplate, September 2026
Generated32 GWhIn 2025
Capacity factor18%Share of the most it could make, 2025
Generators1Oldest from 2023

Cement City Solar, LLC in context

Among the 79 solar plants in Michigan in the EIA's inventory, it is the 26th largest, about 0.6% of the state's 3.3 GW of solar capacity.

Lenawee County has 5 power plants of 1 MW or more with 64 MW in all; Cement City Solar, LLC is 31% of that and the largest of 4 solar plants there.

Its capacity factor of 18% in 2025 is close to the 20% typical for solar plants across the US.

The average electricity customer in Lenawee County goes 24 hours a year without power, the 19th most of 83 counties in Michigan. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

01020304050202320242025GWh 32
0102030405020232024202532

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Cement City Solar, LLC (outlined) and other plants in Lenawee County, shaded. 42.084, -84.135.

Plant facts

Operator
AES Distributed Energy
Sector
IPP Non-CHP
Grid operator
MISO
County
Lenawee County, MI
EIA plant ID
64567
Where Michigan's power comes from → Michigan power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
CMCTY Solar Photovoltaic 20 MW 2023 –

Nearby

Other plants in Lenawee County

Blue Elk IV Solar, LLC · 20 MWBlue Elk I Solar, LLC · 20 MWAdrian Energy Associates LLC · 2.4 MWHendershot Solar, LLC · 2.0 MW

Questions

Cement City Solar, LLC, answered

How much power does Cement City Solar, LLC produce?

Cement City Solar, LLC has 20 MW of capacity from one generator. In 2025 it generated 32 GWh, 18% of the most it could have made running flat out all year (its capacity factor).

How many homes does Cement City Solar, LLC power?

Its 2025 output of 32 GWh equals the yearly electricity use of about 4,200 average Michigan homes (635 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Cement City Solar, LLC?

Cement City Solar, LLC is in Lenawee County, Michigan, at about 42.084°, -84.135°. It is one of 5 power plants of 1 MW or more in the county. The average electricity customer in Lenawee County goes 24 hours a year without power, the 19th most of 83 counties in Michigan. The county's page has the full outage record.

Who operates Cement City Solar, LLC?

It is operated by AES Distributed Energy (EIA sector: IPP Non-CHP), and it feeds MISO.

When did Cement City Solar, LLC open?

Its oldest generator still running came online in 2023.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2023–2025). Homes equivalent uses the average Michigan home's 635 kWh a month in 2025. Methodology.