Natural gas power plant · Hamilton, OH

Central Utility Plant Cincinnati

Central Utility Plant Cincinnati is a 47 MW natural gas power plant in Hamilton County, Ohio, operated by University of Cincinnati. Its oldest generator still running came online in 2004. In 2025 it generated 215 GWh, about what 20,000 average Ohio homes use in a year.

Capacity47 MWNameplate, September 2026
Generated215 GWhIn 2025
Capacity factor52%Share of the most it could make, 2025
Generators4Oldest from 2004

Central Utility Plant Cincinnati in context

Among the 48 natural gas plants in Ohio in the EIA's inventory, it is the 29th largest, about 0.2% of the state's 20 GW of natural gas capacity.

Hamilton County has 4 power plants of 1 MW or more with 1.2 GW in all; Central Utility Plant Cincinnati is 4% of that.

Its capacity factor of 52% in 2025 is higher than the 23% typical for natural gas plants across the US.

The average electricity customer in Hamilton County goes 3.8 hours a year without power, the 62nd most of 88 counties in Ohio. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

010020030020182019202020212022202320242025GWh 215
01002003002019202120232025215

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Central Utility Plant Cincinnati (outlined) and other plants in Hamilton County, shaded. 39.135, -84.509.

Plant facts

Operator
University of Cincinnati
Sector
Commercial CHP
Grid operator
PJM
County
Hamilton County, OH
EIA plant ID
57908
  • Natural gas45 MW96%
  • Other1.9 MW4.0%
Where Ohio's power comes from → Ohio power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
STG Natural Gas Fired Combined Cycle 22 MW 2004 –
CTG1 Natural Gas Fired Combined Cycle 12 MW 2004 –
CTG2 Natural Gas Fired Combined Cycle 12 MW 2004 –
P005 Petroleum Liquids 1.9 MW 2004 –

Nearby

Other plants in Hamilton County

Miami Fort · 1.2 GWEast Campus Utility Plant · 6.0 MWParking Lot Array · 3.7 MW

Questions

Central Utility Plant Cincinnati, answered

How much power does Central Utility Plant Cincinnati produce?

Central Utility Plant Cincinnati has 47 MW of capacity from 4 generators. In 2025 it generated 215 GWh, 52% of the most it could have made running flat out all year (its capacity factor).

How many homes does Central Utility Plant Cincinnati power?

Its 2025 output of 215 GWh equals the yearly electricity use of about 20,000 average Ohio homes (874 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Central Utility Plant Cincinnati?

Central Utility Plant Cincinnati is in Hamilton County, Ohio, at about 39.135°, -84.509°. It is one of 4 power plants of 1 MW or more in the county. The average electricity customer in Hamilton County goes 3.8 hours a year without power, the 62nd most of 88 counties in Ohio. The county's page has the full outage record.

Who operates Central Utility Plant Cincinnati?

It is operated by University of Cincinnati (EIA sector: Commercial CHP), and it feeds PJM Interconnection.

When did Central Utility Plant Cincinnati open?

Its oldest generator still running came online in 2004.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Ohio home's 874 kWh a month in 2025. Methodology.