Natural gas power plant · Hamilton, OH
Central Utility Plant Cincinnati
Central Utility Plant Cincinnati is a 47 MW natural gas power plant in Hamilton County, Ohio, operated by University of Cincinnati. Its oldest generator still running came online in 2004. In 2025 it generated 215 GWh, about what 20,000 average Ohio homes use in a year.
Central Utility Plant Cincinnati in context
Among the 48 natural gas plants in Ohio in the EIA's inventory, it is the 29th largest, about 0.2% of the state's 20 GW of natural gas capacity.
Hamilton County has 4 power plants of 1 MW or more with 1.2 GW in all; Central Utility Plant Cincinnati is 4% of that.
Its capacity factor of 52% in 2025 is higher than the 23% typical for natural gas plants across the US.
The average electricity customer in Hamilton County goes 3.8 hours a year without power, the 62nd most of 88 counties in Ohio. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Central Utility Plant Cincinnati (outlined) and other plants in Hamilton County, shaded. 39.135, -84.509.
Plant facts
- Operator
- University of Cincinnati
- Sector
- Commercial CHP
- Grid operator
- PJM
- County
- Hamilton County, OH
- EIA plant ID
- 57908
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| STG | Natural Gas Fired Combined Cycle | 22 MW | 2004 | – |
| CTG1 | Natural Gas Fired Combined Cycle | 12 MW | 2004 | – |
| CTG2 | Natural Gas Fired Combined Cycle | 12 MW | 2004 | – |
| P005 | Petroleum Liquids | 1.9 MW | 2004 | – |
Nearby
Other plants in Hamilton County
Questions
Central Utility Plant Cincinnati, answered
How much power does Central Utility Plant Cincinnati produce?
Central Utility Plant Cincinnati has 47 MW of capacity from 4 generators. In 2025 it generated 215 GWh, 52% of the most it could have made running flat out all year (its capacity factor).
How many homes does Central Utility Plant Cincinnati power?
Its 2025 output of 215 GWh equals the yearly electricity use of about 20,000 average Ohio homes (874 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Central Utility Plant Cincinnati?
Central Utility Plant Cincinnati is in Hamilton County, Ohio, at about 39.135°, -84.509°. It is one of 4 power plants of 1 MW or more in the county. The average electricity customer in Hamilton County goes 3.8 hours a year without power, the 62nd most of 88 counties in Ohio. The county's page has the full outage record.
Who operates Central Utility Plant Cincinnati?
It is operated by University of Cincinnati (EIA sector: Commercial CHP), and it feeds PJM Interconnection.
When did Central Utility Plant Cincinnati open?
Its oldest generator still running came online in 2004.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Ohio home's 874 kWh a month in 2025. Methodology.