Wind power plant · Cheyenne, CO

Cheyenne Ridge Wind Farm

Cheyenne Ridge Wind Farm is a 498 MW wind power plant in Cheyenne County, Colorado, operated by Public Service Co of Colorado. Its oldest generator still running came online in 2020. In 2025 it generated 1.6 TWh, about what 208,000 average Colorado homes use in a year.

Capacity498 MWNameplate, September 2026
Generated1.6 TWhIn 2025
Capacity factor38%Share of the most it could make, 2025
Generators1Oldest from 2020

Cheyenne Ridge Wind Farm in context

Among the 34 wind plants in Colorado in the EIA's inventory, it is the 3rd largest, about 8.5% of the state's 5.9 GW of wind capacity.

Its capacity factor of 38% in 2025 is higher than the 32% typical for wind plants across the US.

The average electricity customer in Cheyenne County goes 14 hours a year without power, the 4th most of 39 counties in Colorado. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

05001,0001,5002,0002,500202020212022202320242025GWh 1,639
05001,0001,5002,0002,5002020202120222023202420251,639

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Cheyenne Ridge Wind Farm (outlined) and other plants in Cheyenne County, shaded. 39.017, -102.211.

Plant facts

Operator
Public Service Co of Colorado
Sector
Electric Utility
Grid operator
PSCO
County
Cheyenne County, CO
EIA plant ID
62952
Where Colorado's power comes from → Colorado power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
CRW01 Onshore Wind Turbine 498 MW 2020 –

Questions

Cheyenne Ridge Wind Farm, answered

How much power does Cheyenne Ridge Wind Farm produce?

Cheyenne Ridge Wind Farm has 498 MW of capacity from one generator. In 2025 it generated 1.6 TWh, 38% of the most it could have made running flat out all year (its capacity factor).

How many homes does Cheyenne Ridge Wind Farm power?

Its 2025 output of 1.6 TWh equals the yearly electricity use of about 208,000 average Colorado homes (658 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Cheyenne Ridge Wind Farm?

Cheyenne Ridge Wind Farm is in Cheyenne County, Colorado, at about 39.017°, -102.211°. The average electricity customer in Cheyenne County goes 14 hours a year without power, the 4th most of 39 counties in Colorado. The county's page has the full outage record.

Who operates Cheyenne Ridge Wind Farm?

It is operated by Public Service Co of Colorado (EIA sector: Electric Utility), and it feeds Public Service Company of Colorado.

When did Cheyenne Ridge Wind Farm open?

Its oldest generator still running came online in 2020.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2020–2025). Homes equivalent uses the average Colorado home's 658 kWh a month in 2025. Methodology.