Wind power plant · Nodaway, MO

Clear Creek Wind

Clear Creek Wind is a 242 MW wind power plant in Nodaway County, Missouri, operated by Clear Creek Wind, LLC. Its oldest generator still running came online in 2020. In 2025 it generated 466 GWh, about what 37,000 average Missouri homes use in a year.

Capacity242 MWNameplate, September 2026
Generated466 GWhIn 2025
Capacity factor22%Share of the most it could make, 2025
Generators2Oldest from 2020

Clear Creek Wind in context

Among the 14 wind plants in Missouri in the EIA's inventory, it is the 4th largest, about 9.9% of the state's 2.5 GW of wind capacity.

Nodaway County has 4 power plants of 1 MW or more with 845 MW in all; Clear Creek Wind is 29% of that and the largest of 3 wind plants there.

Its capacity factor of 22% in 2025 is lower than the 32% typical for wind plants across the US.

The average electricity customer in Nodaway County goes 6.0 hours a year without power, the 41st most of 110 counties in Missouri. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

02004006008001,000202020212022202320242025GWh 466
02004006008001,000202020212022202320242025466

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Clear Creek Wind (outlined) and other plants in Nodaway County, shaded. 40.370, -94.892.

Plant facts

Operator
Clear Creek Wind, LLC
Sector
IPP Non-CHP
Grid operator
AECI
County
Nodaway County, MO
EIA plant ID
63025
Where Missouri's power comes from → Missouri power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
V120 Onshore Wind Turbine 220 MW 2020 –
V110 Onshore Wind Turbine 22 MW 2020 –

Questions

Clear Creek Wind, answered

How much power does Clear Creek Wind produce?

Clear Creek Wind has 242 MW of capacity from 2 generators. In 2025 it generated 466 GWh, 22% of the most it could have made running flat out all year (its capacity factor).

How many homes does Clear Creek Wind power?

Its 2025 output of 466 GWh equals the yearly electricity use of about 37,000 average Missouri homes (1,037 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Clear Creek Wind?

Clear Creek Wind is in Nodaway County, Missouri, at about 40.370°, -94.892°. It is one of 4 power plants of 1 MW or more in the county. The average electricity customer in Nodaway County goes 6.0 hours a year without power, the 41st most of 110 counties in Missouri. The county's page has the full outage record.

Who operates Clear Creek Wind?

It is operated by Clear Creek Wind, LLC (EIA sector: IPP Non-CHP), and it feeds balancing authority AECI.

When did Clear Creek Wind open?

Its oldest generator still running came online in 2020.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2020–2025). Homes equivalent uses the average Missouri home's 1,037 kWh a month in 2025. Methodology.