Solar power plant · Garrett, MD
CPV Backbone Solar
CPV Backbone Solar is a 175 MW solar power plant in Garrett County, Maryland, operated by CPV Backbone Solar, LLC. Its oldest generator still running came online in 2025. In 2025 it generated 7.5 GWh, about what 662 average Maryland homes use in a year.
CPV Backbone Solar in context
Among the 214 solar plants in Maryland in the EIA's inventory, it is the largest, about 12% of the state's 1.4 GW of solar capacity.
Garrett County has 22 power plants of 1 MW or more with 414 MW in all; CPV Backbone Solar is 42% of that and the largest of 16 solar plants there.
The average electricity customer in Garrett County goes 13 hours a year without power, the 1st most of 24 counties in Maryland. The county's page has the full outage record.
Seasons
Month by month, 2025
Where it is
CPV Backbone Solar (outlined) and other plants in Garrett County, shaded. 39.442, -79.202.
Plant facts
- Operator
- CPV Backbone Solar, LLC
- Sector
- IPP Non-CHP
- Grid operator
- PJM
- County
- Garrett County, MD
- EIA plant ID
- 67022
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| BB1 | Solar Photovoltaic | 175 MW | 2025 | – |
Nearby
Other plants in Garrett County
Questions
CPV Backbone Solar, answered
How much power does CPV Backbone Solar produce?
CPV Backbone Solar has 175 MW of capacity from one generator. In 2025 it generated 7.5 GWh.
How many homes does CPV Backbone Solar power?
Its 2025 output of 7.5 GWh equals the yearly electricity use of about 662 average Maryland homes (944 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is CPV Backbone Solar?
CPV Backbone Solar is in Garrett County, Maryland, at about 39.442°, -79.202°. It is one of 22 power plants of 1 MW or more in the county. The average electricity customer in Garrett County goes 13 hours a year without power, the 1st most of 24 counties in Maryland. The county's page has the full outage record.
Who operates CPV Backbone Solar?
It is operated by CPV Backbone Solar, LLC (EIA sector: IPP Non-CHP), and it feeds PJM Interconnection.
When did CPV Backbone Solar open?
Its oldest generator still running came online in 2025.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2025–2025). Homes equivalent uses the average Maryland home's 944 kWh a month in 2025. Methodology.