Wind power plant · Clark, SD

Crocker Wind Farm

Crocker Wind Farm is a 200 MW wind power plant in Clark County, South Dakota, operated by Geronimo Power. Its oldest generator still running came online in 2019. In 2025 it generated 787 GWh, about what 67,000 average South Dakota homes use in a year.

Capacity200 MWNameplate, September 2026
Generated787 GWhIn 2025
Capacity factor45%Share of the most it could make, 2025
Generators1Oldest from 2019

Crocker Wind Farm in context

Among the 25 wind plants in South Dakota in the EIA's inventory, it is the 8th largest, about 5.8% of the state's 3.5 GW of wind capacity.

Clark County has 3 power plants of 1 MW or more with 222 MW in all; Crocker Wind Farm is 90% of that and the largest of 2 wind plants there.

Its capacity factor of 45% in 2025 is higher than the 32% typical for wind plants across the US.

The average electricity customer in Clark County goes 9.9 hours a year without power. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

02004006008001,0002019202020212022202320242025GWh 787
02004006008001,0002019202120232025787

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Crocker Wind Farm (outlined) and other plants in Clark County, shaded. 45.052, -97.826.

Plant facts

Operator
Geronimo Power
Sector
IPP Non-CHP
Grid operator
MISO
County
Clark County, SD
EIA plant ID
60505
Where South Dakota's power comes from → South Dakota power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
CRCKR Onshore Wind Turbine 200 MW 2019 –

Nearby

Other plants in Clark County

Oak Tree Energy · 20 MWClark (SD) · 2.7 MW

Questions

Crocker Wind Farm, answered

How much power does Crocker Wind Farm produce?

Crocker Wind Farm has 200 MW of capacity from one generator. In 2025 it generated 787 GWh, 45% of the most it could have made running flat out all year (its capacity factor).

How many homes does Crocker Wind Farm power?

Its 2025 output of 787 GWh equals the yearly electricity use of about 67,000 average South Dakota homes (984 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Crocker Wind Farm?

Crocker Wind Farm is in Clark County, South Dakota, at about 45.052°, -97.826°. It is one of 3 power plants of 1 MW or more in the county. The average electricity customer in Clark County goes 9.9 hours a year without power. The county's page has the full outage record.

Who operates Crocker Wind Farm?

It is operated by Geronimo Power (EIA sector: IPP Non-CHP), and it feeds MISO.

When did Crocker Wind Farm open?

Its oldest generator still running came online in 2019.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2019–2025). Homes equivalent uses the average South Dakota home's 984 kWh a month in 2025. Methodology.