Solar power plant · Miami, OH
DG AMP Solar Piqua Manier
DG AMP Solar Piqua Manier is a 13 MW solar power plant in Miami County, Ohio, operated by DG AMP Solar, LLC. Its oldest generator still running came online in 2019. In 2025 it generated 20 GWh, about what 1,900 average Ohio homes use in a year.
DG AMP Solar Piqua Manier in context
Among the 77 solar plants in Ohio in the EIA's inventory, it is the 36th largest, about 0.3% of the state's 5.0 GW of solar capacity.
Miami County has 3 power plants of 1 MW or more with 51 MW in all; DG AMP Solar Piqua Manier is 25% of that and the largest of 2 solar plants there.
Its capacity factor of 18% in 2025 is close to the 20% typical for solar plants across the US.
The average electricity customer in Miami County goes 2.8 hours a year without power, the 76th most of 88 counties in Ohio. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
DG AMP Solar Piqua Manier (outlined) and other plants in Miami County, shaded. 40.130, -84.255.
Plant facts
- Operator
- DG AMP Solar, LLC
- Sector
- IPP Non-CHP
- Grid operator
- PJM
- County
- Miami County, OH
- EIA plant ID
- 62792
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| AMPPM | Solar Photovoltaic | 13 MW | 2019 | – |
Nearby
Other plants in Miami County
Questions
DG AMP Solar Piqua Manier, answered
How much power does DG AMP Solar Piqua Manier produce?
DG AMP Solar Piqua Manier has 13 MW of capacity from one generator. In 2025 it generated 20 GWh, 18% of the most it could have made running flat out all year (its capacity factor).
How many homes does DG AMP Solar Piqua Manier power?
Its 2025 output of 20 GWh equals the yearly electricity use of about 1,900 average Ohio homes (874 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is DG AMP Solar Piqua Manier?
DG AMP Solar Piqua Manier is in Miami County, Ohio, at about 40.130°, -84.255°. It is one of 3 power plants of 1 MW or more in the county. The average electricity customer in Miami County goes 2.8 hours a year without power, the 76th most of 88 counties in Ohio. The county's page has the full outage record.
Who operates DG AMP Solar Piqua Manier?
It is operated by DG AMP Solar, LLC (EIA sector: IPP Non-CHP), and it feeds PJM Interconnection.
When did DG AMP Solar Piqua Manier open?
Its oldest generator still running came online in 2019.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2019–2025). Homes equivalent uses the average Ohio home's 874 kWh a month in 2025. Methodology.