Natural gas power plant · Muskingum, OH

Dresden Energy Facility

Dresden Energy Facility is a 678 MW natural gas power plant in Muskingum County, Ohio, operated by Appalachian Power Co. Its oldest generator still running came online in 2012. In 2025 it generated 4.2 TWh, about what 399,000 average Ohio homes use in a year.

Capacity678 MWNameplate, September 2026
Generated4.2 TWhIn 2025
Capacity factor71%Share of the most it could make, 2025
Generators3Oldest from 2012

Dresden Energy Facility in context

Among the 48 natural gas plants in Ohio in the EIA's inventory, it is the 15th largest, about 3.5% of the state's 20 GW of natural gas capacity.

Its capacity factor of 71% in 2025 is higher than the 23% typical for natural gas plants across the US.

The average electricity customer in Muskingum County goes 4.9 hours a year without power, the 50th most of 88 counties in Ohio. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

02,0004,0006,00020182019202020212022202320242025GWh 4,189
02,0004,0006,00020192021202320254,189

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Dresden Energy Facility (outlined) and other plants in Muskingum County, shaded. 40.093, -82.028.

Plant facts

Operator
Appalachian Power Co
Sector
Electric Utility
Grid operator
PJM
County
Muskingum County, OH
EIA plant ID
55350
Where Ohio's power comes from → Ohio power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
3 Natural Gas Fired Combined Cycle 281 MW 2012 –
1 Natural Gas Fired Combined Cycle 199 MW 2012 –
2 Natural Gas Fired Combined Cycle 199 MW 2012 –

Questions

Dresden Energy Facility, answered

How much power does Dresden Energy Facility produce?

Dresden Energy Facility has 678 MW of capacity from 3 generators. In 2025 it generated 4.2 TWh, 71% of the most it could have made running flat out all year (its capacity factor).

How many homes does Dresden Energy Facility power?

Its 2025 output of 4.2 TWh equals the yearly electricity use of about 399,000 average Ohio homes (874 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Dresden Energy Facility?

Dresden Energy Facility is in Muskingum County, Ohio, at about 40.093°, -82.028°. The average electricity customer in Muskingum County goes 4.9 hours a year without power, the 50th most of 88 counties in Ohio. The county's page has the full outage record.

Who operates Dresden Energy Facility?

It is operated by Appalachian Power Co (EIA sector: Electric Utility), and it feeds PJM Interconnection.

When did Dresden Energy Facility open?

Its oldest generator still running came online in 2012.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Ohio home's 874 kWh a month in 2025. Methodology.