Wind power plant · Guthrie, IA

Eclipse Wind Farm

Eclipse Wind Farm is a 207 MW wind power plant in Guthrie County, Iowa, operated by MidAmerican Energy Co. Its oldest generator still running came online in 2012. In 2025 it generated 832 GWh, about what 81,000 average Iowa homes use in a year.

Capacity207 MWNameplate, September 2026
Generated832 GWhIn 2025
Capacity factor46%Share of the most it could make, 2025
Generators1Oldest from 2012

Eclipse Wind Farm in context

Among the 123 wind plants in Iowa in the EIA's inventory, it is the 19th largest, about 1.5% of the state's 13 GW of wind capacity.

Guthrie County has 3 power plants of 1 MW or more with 214 MW in all; Eclipse Wind Farm is 97% of that.

Its capacity factor of 46% in 2025 is higher than the 32% typical for wind plants across the US.

The average electricity customer in Guthrie County goes 4.2 hours a year without power, the 40th most of 98 counties in Iowa. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

02004006008001,00020182019202020212022202320242025GWh 832
02004006008001,0002019202120232025832

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Eclipse Wind Farm (outlined) and other plants in Guthrie County, shaded. 41.555, -94.685.

Plant facts

Operator
MidAmerican Energy Co
Sector
Electric Utility
Grid operator
MISO
County
Guthrie County, IA
EIA plant ID
57873
Where Iowa's power comes from → Iowa power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
EWF Onshore Wind Turbine 207 MW 2012 –

Nearby

Other plants in Guthrie County

Panora · 4.5 MWStuart (IA) · 2.8 MW

Questions

Eclipse Wind Farm, answered

How much power does Eclipse Wind Farm produce?

Eclipse Wind Farm has 207 MW of capacity from one generator. In 2025 it generated 832 GWh, 46% of the most it could have made running flat out all year (its capacity factor).

How many homes does Eclipse Wind Farm power?

Its 2025 output of 832 GWh equals the yearly electricity use of about 81,000 average Iowa homes (861 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Eclipse Wind Farm?

Eclipse Wind Farm is in Guthrie County, Iowa, at about 41.555°, -94.685°. It is one of 3 power plants of 1 MW or more in the county. The average electricity customer in Guthrie County goes 4.2 hours a year without power, the 40th most of 98 counties in Iowa. The county's page has the full outage record.

Who operates Eclipse Wind Farm?

It is operated by MidAmerican Energy Co (EIA sector: Electric Utility), and it feeds MISO.

When did Eclipse Wind Farm open?

Its oldest generator still running came online in 2012.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Iowa home's 861 kWh a month in 2025. Methodology.