Solar power plant · Sullivan, IN
Fairbanks Solar Project
Fairbanks Solar Project is a 250 MW solar power plant in Sullivan County, Indiana, operated by Fairbanks Solar Energy Center LLC. Its oldest generator still running came online in 2025. In 2025 it generated 358 GWh, about what 32,000 average Indiana homes use in a year.
Fairbanks Solar Project in context
Among the 124 solar plants in Indiana in the EIA's inventory, it is the 4th largest, about 4.9% of the state's 5.1 GW of solar capacity.
Sullivan County has 5 power plants of 1 MW or more with 1.5 GW in all; Fairbanks Solar Project is 16% of that and the largest of 3 solar plants there.
The average electricity customer in Sullivan County goes 5.5 hours a year without power, the 31st most of 90 counties in Indiana. The county's page has the full outage record.
Seasons
Month by month, 2025
Where it is
Fairbanks Solar Project (outlined) and other plants in Sullivan County, shaded. 39.193, -87.524.
Plant facts
- Operator
- Fairbanks Solar Energy Center LLC
- Sector
- Electric Utility
- Grid operator
- MISO
- County
- Sullivan County, IN
- EIA plant ID
- 68429
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| FBNKS | Solar Photovoltaic | 250 MW | 2025 | – |
Nearby
Other plants in Sullivan County
Questions
Fairbanks Solar Project, answered
How much power does Fairbanks Solar Project produce?
Fairbanks Solar Project has 250 MW of capacity from one generator. In 2025 it generated 358 GWh.
How many homes does Fairbanks Solar Project power?
Its 2025 output of 358 GWh equals the yearly electricity use of about 32,000 average Indiana homes (938 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Fairbanks Solar Project?
Fairbanks Solar Project is in Sullivan County, Indiana, at about 39.193°, -87.524°. It is one of 5 power plants of 1 MW or more in the county. The average electricity customer in Sullivan County goes 5.5 hours a year without power, the 31st most of 90 counties in Indiana. The county's page has the full outage record.
Who operates Fairbanks Solar Project?
It is operated by Fairbanks Solar Energy Center LLC (EIA sector: Electric Utility), and it feeds MISO.
When did Fairbanks Solar Project open?
Its oldest generator still running came online in 2025.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2025–2025). Homes equivalent uses the average Indiana home's 938 kWh a month in 2025. Methodology.