Wind power plant · Sherman, TX
Filet Wind (5) LLC
Filet Wind (5) LLC is a 10 MW wind power plant in Sherman County, Texas, operated by UPC Power Solutions. Its oldest generator still running came online in 2006. In 2025 it generated 11 GWh, about what 803 average Texas homes use in a year.
Filet Wind (5) LLC in context
Among the 230 wind plants in Texas in the EIA's inventory, it is the 221st largest, about 0.0% of the state's 45 GW of wind capacity.
Sherman County has 2 power plants of 1 MW or more with 20 MW in all; Filet Wind (5) LLC is 50% of that and the largest of 2 wind plants there.
Its capacity factor of 12% in 2025 is lower than the 32% typical for wind plants across the US.
The average electricity customer in Sherman County goes 5.6 hours a year without power, the 189th most of 240 counties in Texas. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Filet Wind (5) LLC (outlined) and other plants in Sherman County, shaded. 36.445, -101.876.
Plant facts
- Operator
- UPC Power Solutions
- Sector
- IPP Non-CHP
- Grid operator
- SWPP
- County
- Sherman County, TX
- EIA plant ID
- 56561
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| JDW5 | Onshore Wind Turbine | 10 MW | 2006 | – |
Nearby
Other plants in Sherman County
Questions
Filet Wind (5) LLC, answered
How much power does Filet Wind (5) LLC produce?
Filet Wind (5) LLC has 10 MW of capacity from one generator. In 2025 it generated 11 GWh, 12% of the most it could have made running flat out all year (its capacity factor).
How many homes does Filet Wind (5) LLC power?
Its 2025 output of 11 GWh equals the yearly electricity use of about 803 average Texas homes (1,110 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Filet Wind (5) LLC?
Filet Wind (5) LLC is in Sherman County, Texas, at about 36.445°, -101.876°. It is one of 2 power plants of 1 MW or more in the county. The average electricity customer in Sherman County goes 5.6 hours a year without power, the 189th most of 240 counties in Texas. The county's page has the full outage record.
Who operates Filet Wind (5) LLC?
It is operated by UPC Power Solutions (EIA sector: IPP Non-CHP), and it feeds the Southwest Power Pool.
When did Filet Wind (5) LLC open?
Its oldest generator still running came online in 2006.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Texas home's 1,110 kWh a month in 2025. Methodology.