Natural gas power plant · Lyon, NV
Fort Churchill
Fort Churchill is a 230 MW natural gas power plant in Lyon County, Nevada, operated by Sierra Pacific Power Co. Its oldest generator still running came online in 1968. In 2025 it generated 469 GWh, about what 45,000 average Nevada homes use in a year.
Fort Churchill in context
Among the 17 natural gas plants in Nevada in the EIA's inventory, it is the 11th largest, about 2.4% of the state's 9.4 GW of natural gas capacity.
Lyon County has 4 power plants of 1 MW or more with 282 MW in all; Fort Churchill is 81% of that.
Its capacity factor of 23% in 2025 is close to the 23% typical for natural gas plants across the US.
The average electricity customer in Lyon County goes 3.7 hours a year without power, the 7th most of 12 counties in Nevada. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Fort Churchill (outlined) and other plants in Lyon County, shaded. 39.128, -119.132.
Plant facts
- Operator
- Sierra Pacific Power Co
- Sector
- Electric Utility
- Grid operator
- NEVP
- County
- Lyon County, NV
- EIA plant ID
- 2330
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| 1 | Natural Gas Steam Turbine | 115 MW | 1968 | 2028 |
| 2 | Natural Gas Steam Turbine | 115 MW | 1971 | 2028 |
Nearby
Other plants in Lyon County
Questions
Fort Churchill, answered
How much power does Fort Churchill produce?
Fort Churchill has 230 MW of capacity from 2 generators. In 2025 it generated 469 GWh, 23% of the most it could have made running flat out all year (its capacity factor).
How many homes does Fort Churchill power?
Its 2025 output of 469 GWh equals the yearly electricity use of about 45,000 average Nevada homes (868 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Fort Churchill?
Fort Churchill is in Lyon County, Nevada, at about 39.128°, -119.132°. It is one of 4 power plants of 1 MW or more in the county. The average electricity customer in Lyon County goes 3.7 hours a year without power, the 7th most of 12 counties in Nevada. The county's page has the full outage record.
Who operates Fort Churchill?
It is operated by Sierra Pacific Power Co (EIA sector: Electric Utility), and it feeds NV Energy.
When did Fort Churchill open?
Its oldest generator still running came online in 1968. Planned retirements are scheduled for 2028.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Nevada home's 868 kWh a month in 2025. Methodology.