Coal power plant · Sumner, TN

Gallatin (TN)

Gallatin (TN) is a 1.9 GW coal power plant in Sumner County, Tennessee, operated by Tennessee Valley Authority. Its oldest generator still running came online in 1956. In 2025 it generated 4.3 TWh, about what 305,000 average Tennessee homes use in a year.

Capacity1.9 GWNameplate, September 2026
Generated4.3 TWhIn 2025
Capacity factor26%Share of the most it could make, 2025
Generators12Oldest from 1956

Gallatin (TN) in context

Among the 4 coal plants in Tennessee in the EIA's inventory, it is the 2nd largest, about 30% of the state's 6.4 GW of coal capacity.

Sumner County has 2 power plants of 1 MW or more with 2.0 GW in all; Gallatin (TN) is 95% of that.

Its capacity factor of 26% in 2025 is lower than the 45% typical for coal plants across the US.

The average electricity customer in Sumner County goes 4.5 hours a year without power, the 40th most of 73 counties in Tennessee. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

02,0004,0006,00020182019202020212022202320242025GWh 4,324
02,0004,0006,00020192021202320254,324

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Gallatin (TN) (outlined) and other plants in Sumner County, shaded. 36.316, -86.401.

Plant facts

Operator
Tennessee Valley Authority
Sector
Electric Utility
Grid operator
TVA
County
Sumner County, TN
EIA plant ID
3403
  • Coal1.3 GW65%
  • Natural gas663 MW35%
Where Tennessee's power comes from → Tennessee power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
3 Conventional Steam Coal 328 MW 1959 2031
4 Conventional Steam Coal 328 MW 1959 2031
1 Conventional Steam Coal 300 MW 1956 2031
2 Conventional Steam Coal 300 MW 1957 2031
GT5 Natural Gas Fired Combustion Turbine 85 MW 2000 2031
GT6 Natural Gas Fired Combustion Turbine 85 MW 2000 2031
GT7 Natural Gas Fired Combustion Turbine 85 MW 2000 2031
GT8 Natural Gas Fired Combustion Turbine 85 MW 2000 2031
GT1 Natural Gas Fired Combustion Turbine 81 MW 1975 2031
GT2 Natural Gas Fired Combustion Turbine 81 MW 1975 2031
GT3 Natural Gas Fired Combustion Turbine 81 MW 1975 2031
GT4 Natural Gas Fired Combustion Turbine 81 MW 1975 2031

Nearby

Other plants in Sumner County

Questions

Gallatin (TN), answered

How much power does Gallatin (TN) produce?

Gallatin (TN) has 1.9 GW of capacity from 12 generators. In 2025 it generated 4.3 TWh, 26% of the most it could have made running flat out all year (its capacity factor).

How many homes does Gallatin (TN) power?

Its 2025 output of 4.3 TWh equals the yearly electricity use of about 305,000 average Tennessee homes (1,180 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Gallatin (TN)?

Gallatin (TN) is in Sumner County, Tennessee, at about 36.316°, -86.401°. It is one of 2 power plants of 1 MW or more in the county. The average electricity customer in Sumner County goes 4.5 hours a year without power, the 40th most of 73 counties in Tennessee. The county's page has the full outage record.

Who operates Gallatin (TN)?

It is operated by Tennessee Valley Authority (EIA sector: Electric Utility), and it feeds the Tennessee Valley Authority.

When did Gallatin (TN) open?

Its oldest generator still running came online in 1956. Planned retirements are scheduled for 2031.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Tennessee home's 1,180 kWh a month in 2025. Methodology.