Natural gas power plant · Washington, MS

Gerald Andrus

Gerald Andrus is a 781 MW natural gas power plant in Washington County, Mississippi, operated by Entergy Mississippi LLC. Its oldest generator still running came online in 1975. In 2025 it generated 567 GWh, about what 40,000 average Mississippi homes use in a year.

Capacity781 MWNameplate, September 2026
Generated567 GWhIn 2025
Capacity factor8%Share of the most it could make, 2025
Generators1Oldest from 1975

Gerald Andrus in context

Among the 28 natural gas plants in Mississippi in the EIA's inventory, it is the 10th largest, about 5.7% of the state's 14 GW of natural gas capacity.

Its capacity factor of 8% in 2025 is lower than the 23% typical for natural gas plants across the US.

The average electricity customer in Washington County goes 7.2 hours a year without power, the 51st most of 74 counties in Mississippi. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

02004006008001,0001,20020182019202020212022202320242025GWh 567
02004006008001,0001,2002019202120232025567

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Gerald Andrus (outlined) and other plants in Washington County, shaded. 33.350, -91.117.

Plant facts

Operator
Entergy Mississippi LLC
Sector
Electric Utility
Grid operator
MISO
County
Washington County, MS
EIA plant ID
8054
Where Mississippi's power comes from → Mississippi power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
1 Natural Gas Steam Turbine 781 MW 1975 2035

Questions

Gerald Andrus, answered

How much power does Gerald Andrus produce?

Gerald Andrus has 781 MW of capacity from one generator. In 2025 it generated 567 GWh, 8% of the most it could have made running flat out all year (its capacity factor).

How many homes does Gerald Andrus power?

Its 2025 output of 567 GWh equals the yearly electricity use of about 40,000 average Mississippi homes (1,184 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Gerald Andrus?

Gerald Andrus is in Washington County, Mississippi, at about 33.350°, -91.117°. The average electricity customer in Washington County goes 7.2 hours a year without power, the 51st most of 74 counties in Mississippi. The county's page has the full outage record.

Who operates Gerald Andrus?

It is operated by Entergy Mississippi LLC (EIA sector: Electric Utility), and it feeds MISO.

When did Gerald Andrus open?

Its oldest generator still running came online in 1975. Planned retirements are scheduled for 2035.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Mississippi home's 1,184 kWh a month in 2025. Methodology.