Wind power plant · Meagher, MT

Gordon Butte Wind LLC

Gordon Butte Wind LLC is a 18 MW wind power plant in Meagher County, Montana, operated by Gordon Butte Wind LLC. Its oldest generator still running came online in 2012. In 2025 it generated 67 GWh, about what 6,500 average Montana homes use in a year.

Capacity18 MWNameplate, September 2026
Generated67 GWhIn 2025
Capacity factor43%Share of the most it could make, 2025
Generators4Oldest from 2012

Gordon Butte Wind LLC in context

Among the 23 wind plants in Montana in the EIA's inventory, it is the 17th largest, about 0.8% of the state's 2.1 GW of wind capacity.

Its capacity factor of 43% in 2025 is higher than the 32% typical for wind plants across the US.

The average electricity customer in Meagher County goes 33 hours a year without power, the 1st most of 35 counties in Montana. The county's page has the full outage record.

Output

Generation, year by year

Net generation in GWh, as reported to the EIA on Form 923.

02040608010020182019202020212022202320242025GWh 67
020406080100201920212023202567

Seasons

Month by month, 2025

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

Where it is

Gordon Butte Wind LLC (outlined) and other plants in Meagher County, shaded. 46.412, -110.338.

Plant facts

Operator
Gordon Butte Wind LLC
Sector
IPP Non-CHP
Grid operator
NWMT
County
Meagher County, MT
EIA plant ID
57748
Where Montana's power comes from → Montana power outages →

Equipment

Generators in service

GeneratorTechnologyCapacityOnlinePlanned retirement
GBW Onshore Wind Turbine 9.6 MW 2012 –
DAW Onshore Wind Turbine 2.7 MW 2018 –
OSR Onshore Wind Turbine 2.7 MW 2018 –
SOR Onshore Wind Turbine 2.7 MW 2018 –

Questions

Gordon Butte Wind LLC, answered

How much power does Gordon Butte Wind LLC produce?

Gordon Butte Wind LLC has 18 MW of capacity from 4 generators. In 2025 it generated 67 GWh, 43% of the most it could have made running flat out all year (its capacity factor).

How many homes does Gordon Butte Wind LLC power?

Its 2025 output of 67 GWh equals the yearly electricity use of about 6,500 average Montana homes (853 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.

Where is Gordon Butte Wind LLC?

Gordon Butte Wind LLC is in Meagher County, Montana, at about 46.412°, -110.338°. The average electricity customer in Meagher County goes 33 hours a year without power, the 1st most of 35 counties in Montana. The county's page has the full outage record.

Who operates Gordon Butte Wind LLC?

It is operated by Gordon Butte Wind LLC (EIA sector: IPP Non-CHP), and it feeds balancing authority NWMT.

When did Gordon Butte Wind LLC open?

Its oldest generator still running came online in 2012.

Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2018–2025). Homes equivalent uses the average Montana home's 853 kWh a month in 2025. Methodology.