Wind power plant · Montcalm, MI
Gratiot Farms Wind Project
Gratiot Farms Wind Project is a 150 MW wind power plant in Montcalm County, Michigan, operated by Consumers Energy Co - (MI). Its oldest generator still running came online in 2020. In 2025 it generated 345 GWh, about what 45,000 average Michigan homes use in a year.
Gratiot Farms Wind Project in context
Among the 34 wind plants in Michigan in the EIA's inventory, it is the 10th largest, about 4.0% of the state's 3.8 GW of wind capacity.
Montcalm County has 6 power plants of 1 MW or more with 1.1 GW in all; Gratiot Farms Wind Project is 14% of that.
Its capacity factor of 26% in 2025 is lower than the 32% typical for wind plants across the US.
The average electricity customer in Montcalm County goes 17 hours a year without power, the 31st most of 83 counties in Michigan. The county's page has the full outage record.
Output
Generation, year by year
Net generation in GWh, as reported to the EIA on Form 923.
Seasons
Month by month, 2025
Where it is
Gratiot Farms Wind Project (outlined) and other plants in Montcalm County, shaded. 43.169, -84.865.
Plant facts
- Operator
- Consumers Energy Co - (MI)
- Sector
- Electric Utility
- Grid operator
- MISO
- County
- Montcalm County, MI
- EIA plant ID
- 63687
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| CWP | Onshore Wind Turbine | 150 MW | 2020 | – |
Nearby
Other plants in Montcalm County
Questions
Gratiot Farms Wind Project, answered
How much power does Gratiot Farms Wind Project produce?
Gratiot Farms Wind Project has 150 MW of capacity from one generator. In 2025 it generated 345 GWh, 26% of the most it could have made running flat out all year (its capacity factor).
How many homes does Gratiot Farms Wind Project power?
Its 2025 output of 345 GWh equals the yearly electricity use of about 45,000 average Michigan homes (635 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Gratiot Farms Wind Project?
Gratiot Farms Wind Project is in Montcalm County, Michigan, at about 43.169°, -84.865°. It is one of 6 power plants of 1 MW or more in the county. The average electricity customer in Montcalm County goes 17 hours a year without power, the 31st most of 83 counties in Michigan. The county's page has the full outage record.
Who operates Gratiot Farms Wind Project?
It is operated by Consumers Energy Co - (MI) (EIA sector: Electric Utility), and it feeds MISO.
When did Gratiot Farms Wind Project open?
Its oldest generator still running came online in 2020.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2020–2025). Homes equivalent uses the average Michigan home's 635 kWh a month in 2025. Methodology.