Solar power plant · Meigs, OH
Great Bend Solar Project
Great Bend Solar Project is a 48 MW solar power plant in Meigs County, Ohio, operated by Great Bend Solar LLC. Its oldest generator still running came online in 2025. In 2025 it generated 2.7 GWh, about what 257 average Ohio homes use in a year.
Great Bend Solar Project in context
Among the 77 solar plants in Ohio in the EIA's inventory, it is the 31st largest, about 1.0% of the state's 5.0 GW of solar capacity.
Meigs County has 2 power plants of 1 MW or more with 95 MW in all; Great Bend Solar Project is 50% of that.
The average electricity customer in Meigs County goes 13 hours a year without power, the 8th most of 88 counties in Ohio. The county's page has the full outage record.
Seasons
Month by month, 2025
Where it is
Great Bend Solar Project (outlined) and other plants in Meigs County, shaded. 39.003, -81.771.
Plant facts
- Operator
- Great Bend Solar LLC
- Sector
- IPP Non-CHP
- Grid operator
- PJM
- County
- Meigs County, OH
- EIA plant ID
- 67834
Equipment
Generators in service
| Generator | Technology | Capacity | Online | Planned retirement |
|---|---|---|---|---|
| GBSP1 | Solar Photovoltaic | 48 MW | 2025 | – |
Nearby
Other plants in Meigs County
Questions
Great Bend Solar Project, answered
How much power does Great Bend Solar Project produce?
Great Bend Solar Project has 48 MW of capacity from one generator. In 2025 it generated 2.7 GWh.
How many homes does Great Bend Solar Project power?
Its 2025 output of 2.7 GWh equals the yearly electricity use of about 257 average Ohio homes (874 kilowatt-hours a month each). Power from a plant goes into the shared grid, so it does not serve any particular homes by itself.
Where is Great Bend Solar Project?
Great Bend Solar Project is in Meigs County, Ohio, at about 39.003°, -81.771°. It is one of 2 power plants of 1 MW or more in the county. The average electricity customer in Meigs County goes 13 hours a year without power, the 8th most of 88 counties in Ohio. The county's page has the full outage record.
Who operates Great Bend Solar Project?
It is operated by Great Bend Solar LLC (EIA sector: IPP Non-CHP), and it feeds PJM Interconnection.
When did Great Bend Solar Project open?
Its oldest generator still running came online in 2025.
Sources: U.S. Energy Information Administration, Form EIA-860M generator inventory (September 2026) and Form EIA-923 generation (2025–2025). Homes equivalent uses the average Ohio home's 874 kWh a month in 2025. Methodology.